File #: 23-1531    Version: 2 Name: 10/2/23 2190 S State Street Retaining Wall Change Order 1
Type: Resolution Status: Passed
File created: 10/2/2023 In control: City Council
On agenda: 10/2/2023 Final action: 10/2/2023
Enactment date: 10/2/2023 Enactment #: R-23-353
Title: Resolution to Approve Change Order No. 1 and Ratify Emergency Purchase Order with Z Contractors, Inc. for the 2190 South State Street Retaining Wall Replacement Project, RFP 23-11; ($29,697.48 Increase, Total Contract Amount $209,443.53)
Attachments: 1. R-23-211.pdf, 2. Emergency PO - 2190 State St Retaining Wall.pdf, 3. 2023-06-27_Z CONTRACTORS INC - Construction Agreement (1).pdf, 4. 2023-003_2190_South_State_Street_Retaining_Wall CO1.pdf
Title
Resolution to Approve Change Order No. 1 and Ratify Emergency Purchase Order with Z Contractors, Inc. for the 2190 South State Street Retaining Wall Replacement Project, RFP 23-11; ($29,697.48 Increase, Total Contract Amount $209,443.53)
Memorandum
Attached for your review and approval is a change order to the construction contract with Z Contractors, Inc. for the 2190 South State Street Retaining Wall Replacement Project (RFP 32-11).

This project consists of replacing a city-owned timber retaining wall with a modular block retaining wall. The bid quantity for the modular block wall was calculated incorrectly, as it did not include the buried blocks. The wall was constructed as planned and the total area of the wall was about 40% more than bid quantity. An emergency purchase order was approved by the City Administrator, and this request is to approve that increase retroactively.

The additional contract work for Change Order No. 1 includes the additional block required to construct the wall, additional restoration, and the balancing of all other pay items. The initial contract award, including contingency equaled $197,746.05. The total amount for Change Order 1 is $29,697.48, which exceeds the contingency originally approved by Council ($18,000.00) by $11,697.48. Change Order 1 will bring the total contract amount to $209,443.53. Since the project is complete, this is the final change order.

The total amount requested in the emergency purchase order, that was approved by the City Administrator, was incorrect due to an error with balancing pay items. The error was corrected and an additional $952.58 was included in Change Order No. 1, for a total of $29,697.48.

Budget/Fiscal Impact: Funding for the project is available in the approved Major Street Fund Capital Budget.
Staff
Prepared by: Nicholas Hutchinson, P.E., City Engineer
Reviewed by: Brian Steglitz, Public Services Area Administrator