Ann Arbor logo
File #: 19-0107    Version: 1 Name: 2/19/19 - 2019 Streetlight Replacement
Type: Resolution Status: Passed
File created: 2/19/2019 In control: City Council
On agenda: 2/19/2019 Final action: 2/19/2019
Enactment date: 2/19/2019 Enactment #: R-19-068
Title: Resolution to Award a Construction Contract to J. Ranck Electric, Inc. for the 2019 Streetlight Replacement Project ($546,924.00, Bid No. ITB-4557)
Attachments: 1. ITB 4557 Contract Documents, 2. ITB 4557 Plans, 3. ITB 4557 Bid Tab
Title
Resolution to Award a Construction Contract to J. Ranck Electric, Inc. for the 2019 Streetlight Replacement Project ($546,924.00, Bid No. ITB-4557)
Memorandum
Attached for your review and approval is a resolution to award and enter into a construction contract with J. Ranck Electric, Inc., in the amount of $546,924.00, for the 2019 Streetlight Replacement Project, ITB-4557.

The project includes replacement of 73 streetlights throughout the City that were previously assessed to be in poor condition. Specific project areas targeted by this work include Fourth Avenue between Huron Street and William Street and also Liberty Street between Fifth Avenue and Division Street. This work is for capital maintenance of existing streetlights only. Separate work is being coordinated with DTE and City crews for the installation of new streetlights.
Three (3) bids were received on Thursday, December 20, 2018. The lowest responsible bid was from J. Ranck Electric, Inc. in the amount of $546,924.00. A summary of the bids is attached.

J. Ranck Electric, Inc.
Corby Energy Services, Inc.
Rauhorn Electric, Inc.
$546,924.00
$594,927.50
$811,297.00

Staff recommends awarding a construction contract to J. Ranck Electric, Inc. in the amount of $546,924.00, and approving the City's expenditure of an additional $54,000.00, should it be appropriate for the City to do so in the event of contingencies. It is requested that the total $600,924.00 contract and contingency amount be approved for the life of the project without regard to fiscal year.

J. Ranck Electric, Inc. complies with the requirements of the City's Non-Discrimination and Living Wage ordinances.

Budget Impact: The FY2018-2023 Capital Improvements Plan (CIP) identifies the Streetlight Capital Replacement Project (TR-OT-18-01) and is included in the approved Capital Budget.
Staff
Prepared by: Chris Elenbaas, P.E., Public Works Engineer
Reviewed by: Molly Maciejewski, Public Works Unit Manager
Reviewed by: Cr...

Click here for full text