File #: 22-0582    Version: 1 Name: 4/18//22 Resolution to Approve Contract for Stadium/Washtenaw Utilities Project (E.T. MacKenzie)
Type: Resolution Status: Passed
File created: 4/18/2022 In control: City Council
On agenda: 4/18/2022 Final action: 4/18/2022
Enactment date: 4/18/2022 Enactment #: R-22-109
Title: Resolution to Approve a Construction Contract with E.T. MacKenzie Company for the Stadium/Washtenaw Area Utility Improvements Project ($1,829,900.00)
Attachments: 1. Stadium Service Dr-Water Main.pdf, 2. Final Plan Website FC.pdf, 3. PROPOSAL_ETMacKenzie.pdf, 4. Contract MacKenzie.pdf
Title
Resolution to Approve a Construction Contract with E.T. MacKenzie Company for the Stadium/Washtenaw Area Utility Improvements Project ($1,829,900.00)
Memorandum
Attached for your review and approval, please find a resolution to approve a construction contract between the City of Ann Arbor and E.T. MacKenzie Company in the amount of $1,829,900.00 for the Stadium/Washtenaw Area Utility Improvements Project (RFP 22-15).

The scope of this project includes the following:
* Replacement of watermain on Stadium Service Drive from Washtenaw Avenue to Stadium Boulevard, and resurfacing of the roadway (see attached map)
* Replacement of watermain on Frieze Avenue from Brockman to the east end
* Transfer of water services to a larger main on Winchell Drive from Brockman to 175 feet west of Hall Avenue
* Road resurfacing of the above segments of Winchell and Frieze, as well as the segment of Brockman connecting them
* Installation of new sidewalks where none currently exist on Winchell, Brockman, and Frieze within the project limits
* Drainage structure replacements and/or repairs
* Intermittent curb replacements
* Installation of ADA compliant sidewalk ramps and new and/or improved crosswalks

The construction of the project is scheduled to begin in May 2022 and to be completed in early October 2022.

During the course of the project design, staff held a public meeting and conducted surveys to receive input on various project scope items such as the possibility of reconfiguring the intersection of Brockman and Winchell, and the filling of sidewalk gaps. The results of these efforts can be found summarized on the project website at: https://www.a2gov.org/departments/engineering/Pages/Winchell-Frieze-and-Brockman-Sidewalk-Project.aspx

Engineering staff supervised the creation of plans and contract documents and bid the project through the City's Procurement Unit. On March 14, 2022, two proposals were received for this work. A selection committee comprised of Public Se...

Click here for full text