File #: 08-0236    Version: 1 Name: 040708 - 2008 Street Resurfacing Project
Type: Resolution Status: Passed
File created: 4/7/2008 In control: City Council
On agenda: 4/7/2008 Final action: 4/7/2008
Enactment date: 4/7/2008 Enactment #: R-08-146
Title: Resolution to Award a Construction Contract to Cadillac Asphalt, L.L.C. (Bid No. 3920, $2,797,504.87) for the 2008 Street Resurfacing Project
Attachments: 1. Change Order 1.pdf, 2. Cadillac's Bid

Title

Resolution to Award a Construction Contract to Cadillac Asphalt, L.L.C. (Bid No. 3920, $2,797,504.87) for the 2008 Street Resurfacing Project

Memorandum

Attached for your review and approval is a resolution to award a construction contract to Cadillac Asphalt, L.L.C. in the amount of $2,797,504.87 for the 2008 Street Resurfacing Project. 

 

Public Meetings were held on January 10 and January 16, 2008 to introduce the project to local residents and receive feedback from the residents during the design phase of the project.  City staff gave a brief presentation about the project, and answered questions from the residents.  The discussion focused mainly on the extent of the construction work to be done, what that work would include (sidewalks, drive approaches, etc.), existing drainage problems, effect on trees, schedule, and financing for the project.  The residents attending the meetings were generally in favor of the resurfacing of their respective streets.

 

We have attached the street list, showing the general order in which the streets will be resurfaced.  A list of “alternate” streets is also provided.  Construction is scheduled to begin April 28, 2008 and to be completed in September 2008.

 

The Street Resurfacing Project is created as a unit price contract with the understanding that the actual quantities used in construction will vary.  Reflecting this flexibility, if any streets on the existing list are removed for any reason, such as conflicts with other projects, need for extensive utility repair, or any other unforeseen circumstances, the streets on the alternate list will be substituted in the approximate order listed.  If the funds are depleted prior to the completion of all the streets listed on the attachments, the construction contract will be terminated and the balance of the streets will be deferred to a future Resurfacing Project.

 

Eleven sets of plans and specifications were distributed to contractors, subcontractors, and suppliers who expressed interest in the project.  Three bids were received and opened on February 29, 2008.  The lowest responsible bid, in the amount of $2,797,504.87 is approximately $39,817.00 lower than the engineer's estimate of $2,837,322.00.  A tabulation of the bids is also attached.

 

Cadillac Asphalt, L.L.C. received Human Rights approval on March 1, 2008.  All employees of Cadillac Asphalt, L.L.C., assigned to work on the project will receive compensation in accordance with the Living Wage Ordinance.

 

The project will be funded primarily from the Street Resurfacing Millage.  Additional funding for the project will come from the FY 2008 Water Utilities - Water, Sanitary System, Storm Water Operations & Maintenance Funds (for replacement of structures and minor utility repairs), FY 2008 Local Street Fund - Traffic Calming Budget (for traffic calming improvements on Traver Street), and the University of Michigan (for the University’s cost-share portion of the resurfacing of Maynard Street and Glen Court).

Staff

Prepared by:                     Homayoon Pirooz, P.E., Project Management Manager

Reviewed by:                     Sue F. McCormick, Public Services Administrator

Approved by:                     Roger W. Fraser, City Administrator

 

2008 STREET RESURFACING PROJECT SCHEDULE AND CONSTRUCTION LIMITS

 

GROUP A (April 28 - May 23)                                                               LIMITS

W. Ann Street                                                                                        N. Main to N. Fifth Ave.                     

Maynard Street                                                                                     E. Liberty to E. Jefferson                                                               

Glen Court                                                                                            Fuller to U of M Parking Structure                                                                

                                              

GROUP B (May 27 - June 24)

Linden Street                                                                                          Geddes to S. University

Onondaga Street                                                                                    Geddes to Dorset                     

Berkshire Road                         Hill to Vinewood                     

Martin Place                                                                                  Cambridge to Wells

 

GROUP C (June 24 - July 21)

Arlington Boulevard                                                                                    Devonshire to Heatherway                     

Woodside Road                                                                             Wellingford to Shadford                      

Shadford Road                                                                                     Harding to Brockman                                                               

Medford Road                                                                                        Needham to Manchester                                                               

Buckingham Court                                                                                    Buckingham Rd. to Dead End                     

 

GROUP D (July 21 - August 29)

N. Fourth Avenue                                                                                    Depot to Kingsley                                                               

N. Fifth Avenue                                                                                    Depot to Beakes                     

W. Summit Street (patches)                                                               Brooks to Wildt                     

Sunset Road                                                                                       Spring to Wildt                                          

Foss Street                                                                                      N. Maple to Fulmer

Kirtland Drive                                                                                     W. Stadium to Glen Leven

 

GROUP E (August 29 - September 19)

Farmbrook Court                                                                                    Eisenhower Service Drive to Dead End

Baylis Drive                                                               Beaconsfield to Stone School

Ward Court                                                               Baylis to Dead End

Logan Court                                                               Baylis to Dead End

 

GROUP F (April 28 - July 14)

S. Main Street / Eisenhower Parkway Intersection Reconstruction (work on this intersection will occur simultaneously with Groups A through C)

 

“ALTERNATE” STREETS*

E. Summit Street                                                                                    N. Main St. to Fourth Ave

Lincoln Avenue                                                                                    Cambridge to Wells

Medford Road                                                                                    St. Francis Dr. to Needham

W. Summit Street                                                                                    N. Main St. to Ann Arbor Railroad

 

* If any streets on the existing list are removed for any reason, such as conflicts with other projects, need for extensive utility repair, or any other unforeseen circumstances, the streets on the alternate list will be substituted in the approximate order listed.

 

 BID TABULATION FOR THE 2008 Street Resurfacing Project

 

BID No.:                     3920

BID DATE:                     10:00 a.m., February 29, 2008

FILE No.:                                          2008-004

 

BIDDER                                                                                                                              BID PRICE

 

*                     Cadillac Asphalt, L.L.C.                                                                                    $2,797,504.87

Barrett Paving Materials, Inc.                                                               $2,908,451.80

Ajax Paving Industries, Inc.                                                               $3,467,630.60

 

ENGINEER'S ESTIMATE                                                               $2,837,322.00

 

* Lowest Responsible Bidder

Body

Whereas, The City of Ann Arbor Adopted 2007-2008 Capital Budget includes sufficient funds for the Annual Local and Major Street Resurfacing Programs;

 

Whereas, The 2008 Street Resurfacing Project includes the resurfacing and/or reconstruction of approximately 19 local residential streets and 4 major streets;

 

Whereas, The 2008 Street Resurfacing Project is necessary to maintain high quality streets in the City of Ann Arbor;

 

Whereas, The project generally received support from local residents attending two Public Meetings held on January 10 and January 16, 2008;

 

Whereas, Competitive bids were received by Procurement on February 29, 2008 and Cadillac Asphalt, L.L.C. was the lowest responsible bidder at $2,797,504.87;

 

Whereas, The contractual proposal sets forth the services to be performed by said company, and the payments to be made by the City therefore, all of which are agreeable to the City;

 

Whereas, It is now necessary to enter into a Contract with said company for said construction project; and

 

Whereas, Cadillac Asphalt, L.L.C. received Human Rights approval on March 1, 2008, and its employees will receive compensation in accordance with the Living Wage Ordinance;

 

RESOLVED, That a contract in the amount of $2,797,504.87 be awarded to Cadillac Asphalt, L.L.C. for the construction of the 2008 Street Resurfacing Project;

 

RESOLVED, That the project budget in the amount of $4,092,000.00 be adopted for the life of the project, to be available without regard to fiscal year;

 

RESOLVED, That the Mayor and City Clerk be authorized and directed to execute said contract after approval as to form by the City Attorney and approval as to substance by the City Administrator; and

 

RESOLVED, That a contingency amount of $250,000.00 be established within the project budget and that the City Administrator be authorized to approve additional change orders to the construction contract with Cadillac Asphalt, LLC, not to exceed $250,000.00 in order to satisfactorily complete this project; and

 

RESOLVED, That the City Administrator be authorized to take the necessary administrative actions to implement this resolution.