Ann Arbor logo
File #: 11-0358    Version: 1 Name: 4/19/11 ITB - 4125 S. Fifth Ave. and Vaughn St. Water Main
Type: Resolution Status: Passed
File created: 4/19/2011 In control: City Council
On agenda: 4/19/2011 Final action: 4/19/2011
Enactment date: 4/19/2011 Enactment #: R-11-147
Title: Resolution to Award a Construction Contract to Eagle Excavation, Inc. for the S. Fifth Avenue and Vaughn Street Water Main Replacement Project ($ 448,131.00; Bid No. ITB-4125)
Attachments: 1. BID TABULATION, 2. Location Map
Title
Resolution to Award a Construction Contract to Eagle Excavation, Inc. for the S. Fifth Avenue and Vaughn Street Water Main Replacement Project ($ 448,131.00; Bid No. ITB-4125)
Memorandum
Attached for your review and approval please find a resolution that awards a construction contract to Eagle Excavation, Inc. in the amount of $ 448,131.00 for the S. Fifth Avenue and Vaughn Street Water Main Replacement Project.

The existing water mains on S. Fifth Avenue and Vaughn Street are in poor condition and undersized. This project will replace the existing 4-inch water mains with approximately 360 feet of new 12-inch Ductile Iron water main along S. Fifth Ave. from Liberty St. to Washington St. and 700 feet of new Ductile Iron water main along Vaughn Street from Packard St. to E. University Ave. Following the installation of the water main. The contractor will complete all street restoration work. A public engagement meeting for this project was held on March 9, 2011, with no attendance from the members of the public.

Plans and specifications were made available at several on-line construction bidding sites. Four bids were received and opened on March 10, 2011. The lowest responsible bid submitted by Eagle Excavation, Inc. in the amount of $ 448,131.00 is approximately 18% below the Engineer's Estimate. Attached is a tabulation of the bids received for the project.

Eagle Excavation, Inc. received Human Rights approval on March 11, 2011. All employees of Eagle Excavation, Inc., who will work on the project, will receive compensation in accordance with the Living Wage Ordinance.
Staff
Prepared by: Homayoon Pirooz, P.E., Project Management Manager
Reviewed by: Sue F. McCormick, Public Services Administrator
Approved by: Roger W. Fraser, City Administrator
Body
Whereas, The City of Ann Arbor Adopted Capital Budget includes the S. Fifth Avenue and Vaughn Street Water Main Replacement Project;

Whereas, The existing water mains on S. Fifth Avenue and Vaughn ...

Click here for full text