Title
Resolution to Approve a Bollard Construction Contract with Doan Construction Company
Memorandum
Below for your review and approval is a resolution approving a bollard construction contract between the Ann Arbor Downtown Development Authority ("DDA") and Doan Construction Company for $675,000 and to establish a contingency amount of $67,500.
Background
The Ann Arbor Downtown Development Authority's (DDA) 2026-2055 Development Plan identifies improved event barriers as a priority.
Through the Downtown Area Circulation Study, DDA staff worked closely with City Fire, Police, Emergency Management, Community Services, and Transportation Departments to select two barricade models that meet the established safety, operations, and placemaking needs. These include:
* Meridian Archer 1200 Portable Vehicle Barriers (PVBs)
* Ameristar SP100 Lift-Assist Bollards
The DDA Board authorized an initial purchase of Meridian PVBs in March 2025 and a retractable bollard design and initial bollard purchase in May 2026.
Next Steps
The following resolution authorizes a construction contract with Doan Construction Company to install retractable bollards at fourteen intersection approaches:
Phase 1: 2026 Construction Season - Incorporate retractable bollards into active construction projects at 7 locations:
* Liberty Street at Fourth Ave (both sides of the intersection)
* Ann Street at North Main and the mid-block alley between Fourth and Fifth Ave
* North University at Thayer and Fletcher Street
* Thayer at North University
Phase 2: 2027 Spring Construction - Focus retractable bollard installations to complete the Main Street Summer Streets and Sonic Lunch closure areas.
* W. Washington at Ashley Street and S. Main Street
* W. Liberty at Ashley Street
* East Liberty at Fifth Ave and Division Street
* S. Main Street at William and Washington Streets
2028 and Beyond - Schedule remaining bollard locations following additional operations, maintenance, and feasibility disc...