File #: 26-0774    Version: 1 Name: RES to Approve Contract for Bollard Design and a Contract for Bollard Purchase
Type: Resolution Status: Passed
File created: 5/4/2026 In control: Downtown Development Authority
On agenda: 5/6/2026 Final action: 5/6/2026
Enactment date: 5/6/2026 Enactment #: R-26-173
Title: Resolution to Approve a Bollard Purchase from Ameristar ($381,386), and a Bollard Design and Construction Engineering Contract with Wade Trim ($857,000)
Attachments: 1. 20260505_Wade Trim Bollard Design Contract (1).pdf, 2. Ameristar Barrier Quote 2026.pdf, 3. 4.29.2026_Potential Bollard Locations 2026-2028.pdf, 4. AAFD Bollard Support MEMO.pdf, 5. AAPD Bollard Support Memo.pdf
Title
Resolution to Approve a Bollard Purchase from Ameristar ($381,386), and a Bollard Design and Construction Engineering Contract with Wade Trim ($857,000)

Memorandum
Attached for your review and approval is a resolution approving a design contract between the Ann Arbor Downtown Development Authority ("DDA") and Wade Trim, Inc., for $857,000 and an initial purchase of Ameristar retractable bollards not to exceed $381,386.

Background
The Ann Arbor Downtown Development Authority's (DDA) 2026-2055 Development Plan identifies improved event barriers as a priority.
Through the Downtown Area Circulation Study, DDA staff worked closely with City Fire, Police, Emergency Management, Community Services, and Transportation Departments to select two barricade models that meet the established safety, operations, and placemaking needs. These include:
* Meridian Archer 1200 Portable Vehicle Barriers (PVBs)
* Ameristar SP100 Lift-Assist Bollards
Next Steps
The DDA Board authorized an initial purchase of Meridian PVBs in March 2025. The following resolution authorizing bollard design and purchase is the first step to implementing retractable bollards. The Wade Trim Bollard Design and Construction Engineering Contract provides design support through the completion of the retractable bollard project (up to 35 street approaches). The Ameristar bollard quote enables purchase for phase 1 implementation with the active construction projects in 2026. Staff will bring construction-related contracts to a future DDA Board Meeting.
Tentative Bollard Implementation Approach:
* Phase 1: 2026 Construction Season - Incorporate retractable bollards into active construction projects where feasible, including Fourth Ave, Ann Street, and North University.
* Phase: 2027 Spring Construction - Focus retractable bollard installation to complete the Main Street Summer Streets closure area.
* 2028 and Beyond - Schedule remaining bollard locations following additional operations, maintenance, a...