Ann Arbor logo
File #: 10-0446    Version: 1 Name: 5/1710 Argo Dam Consent Agreement
Type: Resolution Status: Passed
File created: 5/3/2010 In control: City Council
On agenda: 5/3/2010 Final action: 5/3/2010
Enactment date: 5/3/2010 Enactment #: R-10-134
Title: Resolution to Approve Consent Agreement to Resolve MDNRE Argo Dam Safety Order Contested Case
Sponsors: Marcia Higgins, Tony Derezinski
Attachments: 1. Argo Dam Consent Agreement, 2. Argo Vegetation Mgmt Plan.pdf, 3. Trigger for Response Actions-Argo Headrace.pdf
Title
Resolution to Approve Consent Agreement to Resolve MDNRE Argo Dam Safety Order Contested Case
Memorandum
On August 6, 2009, the Michigan Department of Natural Resources and Environment (MDNRE; formerly MDEQ) issued a Safety Order that required the City to dewater the Argo Dam headrace and take other actions. The City disagreed with the determinations of the MDNRE and filed a contested case disputing the Order.

The City then negotiated with the MDNRE to allow the City to install a stop log to stop flow into the headrace from Argo Pond at the end of the canoe season while the City installed piezometers to measure water seepage and otherwise undertook further study of the condition of the embankment and the concerns asserted by the MDNRE as grounds for its Order.

Although the City and the MDNRE disagree as to whether there are deficiencies and/or as to the severity of the deficiencies identified by the MDNRE, the City and the MDNRE continued to negotiate and have reached agreement on a Consent Agreement that supersedes the August 6, 2009, Order and resolves the contested case, subject to approval by City Council. The Consent Agreement contains four substantial elements:

1. Provisions for vegetation management;
2. Provisions for emergency response actions;
3. Provisions for monitoring and reporting; and
4. A process and time line for selection of an option to repair the toe drain system and/or reconstruct the embankment.

Copies of the proposed Consent Agreement, Vegetation Management Plan and Triggers for Emergency Response are attached.

Upon execution of the Consent Agreement by both the City and the MDNRE, the City will be able to lift the stop log and resume canoe operations at the Argo livery.
Staff
Prepared by: Sue F. McCormick, Public Services Area Administrator, Sumedh Bahl, Interim Community Services Area Administrator
Reviewed by: Abigail Elias, Chief Assistant City Attorney
Approved by: Roger W. Fraser, City Administrator
Body
Whereas, ...

Click here for full text