File #: 19-0223    Version: 1 Name: 4/1/19- Doan Construction Co. (2019 Sidewalk Repair Program)
Type: Resolution Status: Passed
File created: 4/1/2019 In control: City Council
On agenda: 4/1/2019 Final action: 4/1/2019
Enactment date: 4/1/2019 Enactment #: R-19-125
Title: Resolution to Extend the Contract with Doan Construction Company for the 2019 Sidewalk Repair Program ($658,511.54)
Attachments: 1. 2019 Area Maps.pdf, 2. Doan Contract Extension 2019 Signed.pdf, 3. Item History to Date.pdf, 4. Contract Status.pdf
Title
Resolution to Extend the Contract with Doan Construction Company for the 2019 Sidewalk Repair Program ($658,511.54)
Memorandum
Attached for your review and approval is a resolution to extend the contract with Doan Construction Company (Bid No. 4522) for the Sidewalk Repair Program.

During the past seven construction seasons, the Sidewalk Repair Program has provided repairs to sidewalks throughout the City. Beginning in 2017, the Program returned to neighborhoods repaired in 2012. The attached map shows the areas of the City that will be targeted in 2019.

The Program work included in this agreement consists of the replacement of sidewalk slabs with "vaulted" or "displaced" joints greater than 1 inch in height, and installation of new sidewalk or Americans with Disabilities Act (ADA) compliant ramps.

Doan was the lowest responsible bidder for this kind of work during the last 7 years. Doan's 2018 contract allowed for its renewal for 2 additional years, by mutual agreement, with Doan obliged to hold its bid prices. City staff recommends that Doan's contract be extended for 1 year, and requests that the City Administrator be authorized to extend the contract 1 additional year in 2020, subject to the availability of funding.

Doan has submitted all required Non-Discrimination, Prevailing Wage, Living Wage, and Conflict of Interest Disclosure forms and complies with the requirements of the City's Non-Discrimination, Prevailing Wage and Living Wage ordinances.

Budget Impact: Funding for the project is included in the appropriate approved capital budgets and comes primarily from the Street, Bridge, and Sidewalk Millage; with some additional funding from the Major and Local Street Funds, Washtenaw County Street Millage, Michigan Department of Transportation, Ann Arbor Area Transportation Authority, Downtown Development Authority, and various departmental budgets within the City of Ann Arbor, depending on the location at which the work is done.