File #: 09-0413    Version: 1 Name: 6/15/09 - Arbor Landing Lift Station Generator Installation
Type: Resolution Status: Passed
File created: 6/15/2009 In control: City Council
On agenda: 6/15/2009 Final action: 6/15/2009
Enactment date: 6/15/2009 Enactment #: R-09-222
Title: Resolution to Approve a Contract with Rauhorn Electric, Inc. for the Arbor Landing Lift Station Generator Installation and Electrical Improvements for Wastewater Treatment Services, ITB 4009 ($79,494.00)
Attachments: 1. AA Arbor Landing Electrical Upgrades drawings.pdf
Title
Resolution to Approve a Contract with Rauhorn Electric, Inc. for the Arbor Landing Lift Station Generator Installation and Electrical Improvements for Wastewater Treatment Services, ITB 4009 ($79,494.00)
Memorandum
Your approval is requested to award a contract to Rauhorn Electric, Inc. for $79,494.00 to install a standby generator and implement electrical improvements at the City’s Arbor Landing sewage lift station. This permanent standby generator will increase lift station reliability, minimize the possibility of surcharging sewer lines and flooding basements and reduce staffing expense.

The City has eight sewage lift stations located at seven separate sites. These stations pump sewage through sewers to the City’s Wastewater Treatment Plant (WWTP). The loss of pumping capabilities at a lift station could cause sewage to surcharge the sewer pipes and discharge into private property or the environment. Currently, the WWTP has three permanently installed standby and two mobile generators to supply the power required to maintain pumping at each of the eight lift stations during power outages.

In past extreme weather conditions, electric service to the lift stations has been disrupted for up to several days. During a power outage WWTP staff must quickly move the mobile generators among the sites not equipped with permanent standby generators to assure required pumping of the lift station wet wells. Under these conditions, it may be unavoidable that sewage surcharges into private property or the environment due to the time required to service several sewage lift stations at once.

Over past several years, the installation of emergency generators at the Sequoia, Franklin and Lakewood sewage lift stations has increased overall system reliability. Still, there are more lift stations without permanent standby generators rather than mobile generators available to power them. Staff evaluated the remaining lift station sites based on relevant criteria like: f...

Click here for full text