Title
Resolution to Authorize the Project Management Services Unit to oversee the Proposed Traffic Control Plan for the University of Michigan Construction Project at S. Main Street
Memorandum
Attached for your review and approval is a resolution to authorize City staff to review, approve, and inspect the proposed street lane closure for the University of Michigan construction project at S. Main Street.

In 2008, the University of Michigan began the construction of the West Arcade Wall at its Football Stadium on the east side of S. Main Street, north of Stadium Blvd. To date the construction project has continued without a long term traffic lane closure at S. Main Street. However in 2010, the contractors must complete the Wall which is 90 feet tall at its highest point.

To ensure the safety of the construction workers and the general public, the contractors have proposed a temporary traffic control plan for the construction phase from March 2010 through July 2010. The plan requires the temporary closure of the most easterly traffic lane at S. Main Street, from Snyder Ave to Keech Ave. The traffic control plan includes maintaining one southbound and two northbound traffic lanes on S. Main Street. The plan also includes an alternate route for the southbound traffic using Pauline Blvd, S. Seventh Street and Scio Church Road. We anticipate some use of the alternate route during afternoon rush hours in the weekdays.

In 2010, W. Stadium Blvd will be under construction. In anticipation of the proposed S. Main Street lane closure plan, we have scheduled the W. Stadium construction to include the work between the Pauline Blvd intersection and the S. Seventh intersection for the months of April 2010 through July 2010. After July 2010 and the restoration of all the traffic lanes on S. Main Street, the construction of W. Stadium Blvd at S. Seventh Street will begin.

In 2010, we could begin the construction of the two bridges at E. Stadium Blvd. This project may begin ...