File #: 18-0425    Version: 1 Name: 4/2/18 Kerrytown Liberty Appropriation
Type: Resolution Status: Passed
File created: 4/2/2018 In control: City Council
On agenda: 4/2/2018 Final action: 4/2/2018
Enactment date: 4/2/2018 Enactment #: R-18-115
Title: Resolution to Appropriate the Downtown Development Authority's Contribution to the Liberty Street and Kerrytown Market Street Lighting Replacement Project ($150,038.00) (8 Votes Required)
Attachments: 1. DDA Kerrytown Liberty Cost Sharing Agreement Signed.pdf
Title
Resolution to Appropriate the Downtown Development Authority's Contribution to the Liberty Street and Kerrytown Market Street Lighting Replacement Project ($150,038.00) (8 Votes Required)
Memorandum
On July 3, 2017, City Council passed #R-17-253 authorizing a construction contract to Corby Energy Services for the replacement of Street Lighting in Kerrytown Market and Liberty Street areas. To enable the project to be fully funded, the Downtown Development Authority (DDA) agreed to contribute approximately $150,038.00 towards the construction costs. This resolution seeks to appropriate their contribution of approximately $150,038.00 to the existing project budget.

As mentioned in #R-17-253, an agreement between the City of Ann Arbor and the Downtown Development Authority regarding the responsibilities and cost allocation for the project was to be prepared. The agreement has since been executed and indicates the City to be responsible for management and construction of the project; therefore, requires that the DDA contribution be allocated to the existing project budget. This allows for that funding to be available for contract-required payments.

The construction phase of the project is scheduled to begin this spring and is anticipated to be completed by early summer.
Staff
Prepared by: Marti Praschan, Public Services, Chief of Staff
Reviewed by: Craig Hupy, Public Services Area Administrator
Approved by: Howard S. Lazarus, City Administrator
Body
Whereas, The existing streetlights in the Kerrytown and Liberty Street areas are in poor condition and in need of replacement;

Whereas, The Ann Arbor Downtown Development Authority ("DDA") agreed to contribute approximately $150,038.00 towards the construction costs;

Whereas, The City and the DDA have entered into an agreement indicating the City of Ann Arbor is responsible for the management of the project; and

Whereas, The DDA's contribution must be available for contract related payments; ...