Ann Arbor logo
File #: 16-1547    Version: 1 Name: 11/10/16 2250 Ann Arbor-Saline Road Site Plan and Wetland Use Permit
Type: Resolution/Public Hearing Status: Passed
File created: 11/10/2016 In control: City Council
On agenda: 12/5/2016 Final action: 12/5/2016
Enactment date: 12/5/2016 Enactment #: R-16-467
Title: Resolution to Approve 2250 Ann Arbor-Saline Road Site Plan, Development Agreement and Wetland Use Permit, 2250 Ann Arbor-Saline Road (CPC Recommendation: Approval - 7 Yeas and 0 Nays)
Attachments: 1. August 3, 2016 2250 Ann Arbor Saline Staff Report with Attachments, 2. 2250 Ann Arbor Saline DEV AGR - JUNE 2016, 3. August 3, 2016 CPC Minutes for 2250 Ann Arbor Saline Road Site Plan for Council Approval, 4. October 20, 2015 CPC Minutes
Related files: 16-1144, 16-0644, 15-0920
Title
Resolution to Approve 2250 Ann Arbor-Saline Road Site Plan, Development Agreement and Wetland Use Permit, 2250 Ann Arbor-Saline Road (CPC Recommendation: Approval - 7 Yeas and 0 Nays)
Memorandum
Approval of this resolution will allow for the construction of an 86,576 square foot multiple-family building with 79 underground parking spaces and 51 surface parking spaces.

Petition Summary:

* The Site Plan proposes one residential building that will be a mix of twenty (20) one-bedroom, fifty-three (53) two-bedroom, and two (2) three-bedroom units that will range in size from 785 square feet to 2,098 square feet. The building will be marketed to active adults and will contain a community gathering area, exercise room and outdoor pool. Outdoor amenities will also be provided including a water feature, fire pit, walking paths and outdoor seating areas. There will be a total of 130 parking spaces provided on the site. 79 of these spaces are enclosed underneath the building, with the remaining 51 spaces provided in an exterior parking lot. The site is proposed to be accessed only from Ann Arbor-Saline Road. No vehicular connection is proposed from the Lambeth street stub. A new sidewalk will be constructed that will connect the existing neighborhood to the west to the non-motorized path along Ann Arbor-Saline Road.
* Storm water management will be provided in a detention basin in the southwest corner of the site. Currently no storm water treatment exists for the site. The petitioner and property owner have worked with the City in order to engineer a much larger storm water facility than is required for the impervious surface on the site alone. The extra capacity will provide additional storm water management opportunity, that will benefit the surrounding area. The City and the owner will enter into an easement agreement that covers the construction and management of the regional detention basin.
* A wetland use permit is also required for the remo...