File #: 16-0645    Version: 1 Name: 6/6/16- broadway-division wall repairs
Type: Resolution Status: Passed
File created: 6/6/2016 In control: City Council
On agenda: 6/6/2016 Final action: 6/6/2016
Enactment date: 6/6/2016 Enactment #: R-16-216
Title: Resolution to approve a Construction Contract with Lacaria Concrete Construction, Inc. for the Broadway/Division/Detroit Street Planter Wall and Sidewalk Repair Project ($55,078.00)
Attachments: 1. contract documents - planter wall repairs - 160426, 2. lacaria concrete construction - original bid submittal - 160420
Title
Resolution to approve a Construction Contract with Lacaria Concrete Construction, Inc. for the Broadway/Division/Detroit Street Planter Wall and Sidewalk Repair Project ($55,078.00)
Memorandum
Attached for your review and approval, please find a resolution that approves a construction contract between Lacaria Concrete Construction, Inc. and the City of Ann Arbor for the Broadway/Division/Detroit Street Planter Wall and Sidewalk Repair Project.

Budget/Fiscal Impact
The estimated total cost of the project is $80,000.00. The work of this project will be interim funded through Fund 0062 (the Street Resurfacing Millage) until the City recovers its cost from the insurance company that is representing the driver of the vehicle that damaged the wall.

Project Description
The Broadway/Division/Detroit Street Planter Wall and Sidewalk Repair Project is a minor project that was necessary due to an accident that occurred on September 22, 2015 when a motorist lost control of their car and struck the southeast corner of the planter wall island that separates North Division/Broadway at the west end of the Broadway Bridge over Depot Street and the Norfolk Southern Railroad tracks and badly damaged it. In order to repair the wall, it is necessary to remove and replace about 14.5 lineal feet of the cast-in-place concrete retaining wall, an adjoining portion of the concrete slope paving, the sidewalk and ramps next to the wall, and restore the area to its pre-construction condition.

The Project Management Services Unit had plans and contract documents prepared for this work and bid the project through the City's Procurement Unit following our standard procedures. On April 20, 2016, three bids were received for this work. Lacaria Concrete Construction, Inc. of Detroit Michigan was the lowest responsible bidder with a bid amount of $55,078.00. A tabulation of the bids received is as follows:

Lacaria Concrete Construction, Inc. $ 55,078.00
Doan Construc...