Title: Resolution to Approve a Contract with Blue Star, Inc. for Property Demolition, Clean Up and Site Restoration at 3013 Huron River Drive ($93,300.00)
Attachments: 1. ITB document
Title
Resolution to Approve a Contract with Blue Star, Inc. for Property Demolition, Clean Up and Site Restoration at 3013 Huron River Drive ($93,300.00)
Memorandum
Attached for your review and action is a resolution to approve a $93,300.00 contract with Blue Star Inc. to demolish an abandoned house, remove debris and contaminated soil, and restore the park property at 3013 Huron River Drive.

The property is approximately 24.45 acres, a portion of which runs along the Huron River, and is adjacent to other City-owned property. On the west side of Huron River Drive, the property is partly wooded with steep slopes and grasslands. The property was donated to the City and included an endowment in the amount of $476,115.99, part of which will be used to demolish the house, remove debris and contaminated soil, and restore the area so that the site can open for public use. The property drive is currently chained shut and signed as not open to the public.

Last year, the City bid the project and awarded it to a contractor who failed to commence the work, resulting in the need to rebid the project. Three bids were received by the City for this project:

Blue Star, Inc. $93,300.00*
E.T. Mackenzie Company $99,990.00
Homrich, Inc. $116,300.00

*Lowest responsible bidder.

Staff is recommending awarding a contract to Blue Star, Inc., Inc. in the amount of $93,300.00 to perform demolition and restoration services. A 10% construction contingency ($9,330.00) is requested to cover potential contract change orders to be approved by the City Administrator. It is requested that a $102,630.00 contract and contingency amount be approved for the life of the project without regard to fiscal year.

The Park Advisory Commission recommended approval of this contract at their May 17, 2016 meeting.
Staff
Prepared by: Amy Kuras, Landscape Architect IV
Reviewed by: Colin Smith, Parks & Recreation Services Manager
Derek Delacourt, Community Services Area Adminis...