File #: 15-0204    Version: 1 Name: 4/6/15 - Payment to Scio Twp for Liberty LS Rehabilitation Project
Type: Resolution Status: Passed
File created: 4/6/2015 In control: City Council
On agenda: 4/6/2015 Final action: 4/6/2015
Enactment date: 4/6/2015 Enactment #: R-15-115
Title: Resolution Authorizing Payment to Scio Township for the City's Share of the Liberty Road Sanitary Lift Station Rehabilitation Project ($160,000.00)
Attachments: 1. MOU for O&M of Liberty Lift Station 12-12
Title
Resolution Authorizing Payment to Scio Township for the City's Share of the Liberty Road Sanitary Lift Station Rehabilitation Project ($160,000.00)
Memorandum
You are requested to authorize payment to Scio Township (Scio) for the City of Ann Arbor's share of capital expenses for the Liberty Road Sanitary Sewer Lift Station (Liberty LS) Rehabilitation Project in an amount up to $160,000.00.

Liberty LS is located in Scio and receives sanitary sewer flow from both the City and the Township. Both parties continue to be involved and impacted by the operation and maintenance (O&M) of Liberty LS, which was constructed by the Washtenaw Intermediate School District under an agreement, dated January 29, 1974.

On November 8, 2012, Council approved a Memorandum of Understanding (MOU) agreement between the City and Scio for the continued O&M and improvement of Liberty LS, and to define the maintenance and cost sharing arrangement for these purposes. The MOU stipulates that Scio pays 90% and the City pays 10% of the costs associated with the routine O&M of Liberty LS, which is the City's responsibility. Scio reimburses the City for its portion of these O&M costs. Further, the MOU states that Scio pays 85% and the City pays 15% of the costs that are capital in nature. Scio undertook the Liberty LS Rehabilitation Project, and consistent with the terms of the MOU, you are asked to authorize the City to reimburse Scio for 15% of the costs for this project based on invoices submitted by Scio to the City.

The most recent draft cash flow schedule for the Liberty LS Rehabilitation Project as developed by Scio's consultant engineer estimates the City's costs to be $142,500.00 for this project. This estimate does not include a project contingency, which City staff would typically include for construction work involving underground utilities and keeping a facility in service during rehabilitation and replacement of equipment. Consequently, you are requested to a...