Ann Arbor logo
File #: 13-1045    Version: 1 Name: 10/7/13 - Demolition of Farmhouse, Barns at Wheeler Service Center
Type: Resolution Status: Passed
File created: 10/7/2013 In control: City Council
On agenda: 10/7/2013 Final action: 10/7/2013
Enactment date: 10/7/2013 Enactment #: R-13-295
Title: Resolution to Approve a Contract with TSP Services, Inc. for the Demolition of Farmhouse, Barns and Outbuildings at Wheeler Service Center, ITB-4268 ($57,940.00)
Attachments: 1. ITB-4268_contract
Title
Resolution to Approve a Contract with TSP Services, Inc. for the Demolition of Farmhouse, Barns and Outbuildings at Wheeler Service Center, ITB-4268 ($57,940.00)
Memorandum
As part of the Wheeler Service Center Development Agreement the City entered into with Pittsfield Township, the City agreed to raze a farmstead that is located along Ellsworth Road just west of Shadowood Drive. The farmstead buildings are in poor condition and possess no historic significance. The buildings are an unattractive nuisance to humans and animals.

The demolition includes the removal of all structures located on the site, all structure foundations, all miscellaneous concrete and asphalt surfacing, with grading and restoration work consisting of topsoil, seed and mulch.

A lead and asbestos survey was conducted for all structures on the site on March 28, 2013. The survey found lead and asbestos in several of the structures. Abatement and proper, legal disposal are required for all materials on site exceeding federally mandated action levels.

Eight bids were received in response to ITB-4268:

TSP Services, Inc. $ 57,940.00
Able Demolition $ 68,820.00
Dore & Associates Contracting $ 71,100.00
Smalley Construction Company $ 79,250.00
Graham Construction Corporation $ 80,000.00
Blue Star $ 93,950.00
Homrich $ 124,000.00
E.T. MacKenzie Company $ 103,492.00

Staff recommends acceptance of TSP Services, Inc. as the lowest responsible bidder with a bid in the amount of $57,940.00 to demolish all the structures, foundations, miscellaneous concrete and asphalt surfacing and perform grading and restoration work on the farmstead at Wheeler Service Center and approval of a 15% construction contingency in the amount of $8,691.00 to cover potential change orders to be approved by the City Administrator, and that the $66,631.00 be approved for the life of the project. Funds are available in the Wheeler Maintenance Facility capital project bud...

Click here for full text