Ann Arbor logo
File #: 12-0353    Version: 1 Name: 4/16/12 - City Hall Unisex Restroom Contract Award
Type: Resolution Status: Passed
File created: 4/16/2012 In control: City Council
On agenda: 4/16/2012 Final action: 4/16/2012
Enactment date: 4/16/2012 Enactment #: R-12-139
Title: Resolution to Approve a Contract with LC Construction, LLC for the Construction of Unisex Restrooms in the Guy C. Larcom City Hall Building ($93,438.00)
Attachments: 1. 041612 Agenda - ITB 4203 bid tab.pdf, 2. Larcom Unisex Bathroom Contract.pdf
Title
Resolution to Approve a Contract with LC Construction, LLC for the Construction of Unisex Restrooms in the Guy C. Larcom City Hall Building ($93,438.00)
Memorandum
We recommend your approval of the attached resolution authorizing a contract in the amount of $93,438.00, with LC Construction, LLC, for the construction of unisex restrooms at City Hall. The project involves the construction of five unisex restrooms, on floors 2-6, in the old elevator tower of City Hall. The proposed restrooms on floors 2-6 would match, in fit and finish, the two unisex restrooms that were recently constructed in the basement and first floor as part of the A2MC Project. Completion of this project allows the City to offer a fully ADA accessible restroom on each floor for the public and staff utilizing this facility.

This project is the start of a two year project to improve the restroom facilities in City Hall. The restrooms in the building are nearly 50 years old and many have deteriorating pipes and fixtures. Repair of the restrooms in the west end of City Hall is also hampered by the presence of asbestos containing materials. Work to remove this asbestos is being planned for yet this fiscal year. Repairs and updates to the existing east and west restrooms on each floor are planned for next fiscal year if funding is approved.

Requests for bids were advertised and bids were received from eleven contractors on March 2, 2012. Staff evaluated the bids and determined that the prices were competitive and recommends that LC Construction, LLC, as the lowest responsible bidder, be awarded the contract. The apparent low bidder, DMC Consultants, Inc., requested to withdraw their bid after it was determined that they had omitted some items from their bid price. The bid tabulation is attached.

Funding for this work is budgeted in the Public Services Area, Facilities Maintenance General Fund operating budget for FY12. The resolution includes a recommended project contingency ...

Click here for full text