Ann Arbor logo
File #: 23-2005    Version: 2 Name: 12/18/23 Resolution to Approve a General Services Agreement and to Ratify an Emergency Best Source Purchase Order with Schindler Elevator Corporation
Type: Resolution Status: Passed
File created: 12/18/2023 In control: City Council
On agenda: 12/18/2023 Final action: 12/18/2023
Enactment date: 12/18/2023 Enactment #: R-23-450
Title: Resolution to Approve a General Services Agreement and to Ratify an Emergency Best Source Purchase Order with Schindler Elevator Corporation for the Water Plant Freight Elevator Jack Replacement ($446,104.00)
Attachments: 1. SCHINDLER ELEVATOR CORPORATION - General Services Agreement (GSA).pdf, 2. EPO Memo Shindler elevator (2).pdf, 3. Schindler BEST_SOURCE_JUSTIFICATION_2020_noSignatures.pdf, 4. Elevator Jack replacment SOW.pdf, 5. AA Water Treatment - Jack Replacement + Well drilling.pdf
Title
Resolution to Approve a General Services Agreement and to Ratify an Emergency Best Source Purchase Order with Schindler Elevator Corporation for the Water Plant Freight Elevator Jack Replacement ($446,104.00)
Memorandum
The Water Treatment plant has a high capacity hydraulically operated freight elevator which is used to transport large pieces of equipment, material, and personnel to floors 2-4 of the treatment plant. Access to these areas is critical to routine plant operation and maintenance and for chemical addition and storage and staff cannot safely transport equipment or materials to these upper floors without the elevator.

Recently the elevator failed and during the inspection by Schindler Elevator it was found that the hydraulic jack that goes approximately 60 feet into the ground and lifts the elevator has failed. A new jack that meets current regulations must be installed which will require drilling a new hole to accommodate the size of the new casing and jack assembly.

This elevator is extremely important in day-to-day operations. An emergency purchase order ($446,104.00) was necessary so that the parts could be ordered as there is a 3-month lead time and repair of the elevator needs to occur as quickly as possible to ensure all areas of the facility are safely accessible.

Schindler Elevator Corporation has been servicing the water plant elevators for years. They diagnosed the problem and provided the detailed scope and quote for the repair and are the best source for this work.

Staff recommends that City Council approve a General Service Agreement and to Ratify the Emergency Best Source Purchase Order with Schindler Elevator Corporation to provide service for the Elevator Jack Replacement.

Budget/Fiscal Impact: Funding for this project is available in the Water System Supply Fund Capital Budget.
Staff
Prepared by: Nicholas Baran, Inventory Control Technician
Reviewed by: Molly Maciejewski, Water Treatment Services Ma...

Click here for full text