File #: 18-0008    Version: 1 Name: 2/5/18 - Sister Lake Stormwater Retrofit Construction
Type: Resolution Status: Passed
File created: 2/5/2018 In control: City Council
On agenda: 2/5/2018 Final action: 2/5/2018
Enactment date: 2/5/2018 Enactment #: R-18-031
Title: Resolution to Award a Construction Contract to TSP Services, Inc. (Bid No. 4517) for the First Sister Lake Stormwater Retrofit ($279,857.50)
Attachments: 1. ITB 4517 Bid Summary.pdf, 2. TSP bid submittal.pdf
Title
Resolution to Award a Construction Contract to TSP Services, Inc. (Bid No. 4517) for the First Sister Lake Stormwater Retrofit ($279,857.50)
Memorandum
Attached for your review and approval is a resolution to award a construction contract to TSP Services, Inc. in the amount of $279,857.50 for the First Sister Lake Stormwater Retrofit.

Budget Impact
This project is included in the City's Capital Improvement Plan (CIP) as project UT-ST-16-11, and funding is approved in the Stormwater Capital budget. Any long-term maintenance associated with the proposed work would be budgeted from Stormwater Operations and Maintenance funds.

Background
In 2016, the City initiated public engagement and detailed design for a project to provide water-quality improvements, conveyance modifications, and ecological habitat improvements that will protect and enhance First Sister Lake. The purpose of the project is to remove nutrients from the stormwater that contribute to the degradation of First Sister Lake. The resulting design is a bio-filtration garden that removes the nutrients from the first flush of stormwater runoff from the adjacent neighborhood, before releasing the water into First Sister Lake. The final design was presented to the Parks Advisory Commission in October 2017.

Project specifications were distributed electronically to contractors, subcontractors, and suppliers. Eleven contractors attended the mandatory pre-bid meeting, and four responsive bids were received. The low responsible bidder was TSP Services, Inc., whose bid of $279,857.50 is six percent lower than the Engineer's Estimate of $297,600.

TSP Services, Inc. is in compliance with the requirements of the City's Non-Discrimination and Living Wage ordinances.
Staff
Prepared by: Nicholas Hutchinson, P.E., City Engineer
Reviewed by: Craig Hupy, Public Services Area Administrator
Approved by: Howard S. Lazarus, City Administrator
Body
Whereas, The project will provide water-quality improvements...