File #: 20-0485    Version: 1 Name: 5/4/20 Construction Contract for Barton Drive Project
Type: Resolution Status: Passed
File created: 5/4/2020 In control: City Council
On agenda: 5/4/2020 Final action: 5/4/2020
Enactment date: 5/4/2020 Enactment #: R-20-147
Title: Resolution to Award a Construction Contract to Bailey Excavating, Inc. for the Barton Drive Water Main Replacement and Resurfacing Project ($1,391,453.62)
Attachments: 1. ITB 4617 Barton Drive Construction Contract Revised Blank.pdf, 2. Location Map.pdf, 3. Bailey Compliance Documents.pdf, 4. Bailey Surety Bond.pdf, 5. Barton ITB 4617 Contract.pdf, 6. Bid Tab for Legistar.pdf, 7. Bailey Excavation, Inc Bid.pdf, 8. Low Bid Letter Bailey Exacavting, Inc.pdf
Title
Resolution to Award a Construction Contract to Bailey Excavating, Inc. for the Barton Drive Water Main Replacement and Resurfacing Project ($1,391,453.62)
Memorandum
Attached for your approval is a resolution to award a construction contract to Bailey Excavating in the amount of $1,391,453.62 for the Barton Drive Water Main Replacement and Resurfacing Project ("Project").

Project Description: The Project will replace and upsize water mains on Barton Drive between Northside Avenue and Pontiac Trail. This Project also includes geometric changes to intersections with Brede Place, Longshore Drive, Chandler Road, and Starwick Drive; new sidewalks; new accessible sidewalk ramps; some drainage structure replacements; and street resurfacing between the M14 ramps and Pontiac Trail.

Project plans and specifications were distributed through the City's procurement website. Four (4) bids were received and opened on April 7, 2020. Bailey Excavating, Inc. of Jackson, Michigan, was the lowest responsible bidder with a bid amount of $1,391,453.62, which is 5.46% higher than the Engineer's Estimate of $1,319,352.35. Attached is a summary of the bids received.

Bailey Excavating, Inc. has successfully completed similar work in the City and is able to meet the Project requirements. Bailey Excavating, Inc. has submitted all required Non-Discrimination, Prevailing Wage, Living Wage, and Conflict of Interest Disclosure forms and complies with the requirements of the City's Non-Discrimination and Living Wage ordinances.

A contingency amount of $150,000.00 is requested to cover change orders approved by the City Administrator.

Budget and Fiscal Impact: The Barton Drive Water Main Replacement and Resurfacing Project is included in the approved FY20-25 Capital Improvements Plan (TR-SC-18-03 & UT-WS-18-53). Estimated costs for the project are as follows:

Construction Estimate $1,391,500.00
Planning/Design $ 165,000...