Ann Arbor logo
File #: 15-1361    Version: 1 Name: 12/7/15 - Resolution for Doan Change Order No. 1
Type: Resolution Status: Passed
File created: 12/7/2015 In control: City Council
On agenda: 12/7/2015 Final action: 12/7/2015
Enactment date: 12/7/2015 Enactment #: R-15-405
Title: Resolution to Approve Change Order No. 1 with Doan Construction Company (Bid No. 4320) for the 2015 Ramp & Sidewalk Repair Project ($400,000.00)
Title
Resolution to Approve Change Order No. 1 with Doan Construction Company (Bid No. 4320) for the 2015 Ramp & Sidewalk Repair Project ($400,000.00)
Memorandum
Attached for your review and approval is a change order to the Construction Contract with Doan Construction Company. (Bid No. 4320) for the 2015 Ramp & Sidewalk Repair Project.

Budget Impact
The project is funded from the Street Resurfacing and Sidewalk Repair Millage fund. The construction contract was approved by City Council on March 16, 2015 for a total authorized amount of $2,090,000.00. Change Order No. 1 in the amount of $400,000.00 increases the total authorized amount to $2,490,000.00.

The Project repaired deficient sidewalks in approximately 20% of the City in 2015, as part of the fourth year of the 5-year program to perform repairs on the City's entire sidewalk system. In addition to sidewalk repairs, the project also includes the continued replacement of sidewalk curb ramps to meet the requirements of the Americans with Disabilities Act (ADA) as required by our Consent Decree.

The Ramp & Sidewalk Repair Project is created as a unit price contract with the understanding that the actual construction quantities will vary due to the nature of the work. Quantities of work for are based solely on estimates made at the beginning of the construction season, but field conditions determine the actual amount of work needed, which was greater than anticipated for the 2015 work areas. This increase in authorized quantities provides an opportunity to complete sidewalk repairs and install required ADA compliant ramps in all of the neighborhoods included in this year's work areas.

Doan Construction Company complies with the City's Non-Discrimination and Living Wage Ordinances.
Staff
Prepared by: Nicholas Hutchinson, P.E., City Engineer
Reviewed by: Craig Hupy, Public Services Area Administrator
Approved by: Tom Crawford, Interim City Administrator
Body
Whereas, Funding for the...

Click here for full text