Skip to main content
Ann Arbor logo
File #: 25-2268    Version: 1 Name: 1/20/26 - Fonson Change Order for Westgate Watermain
Type: Resolution Status: Passed
File created: 1/20/2026 In control: City Council
On agenda: 1/20/2026 Final action: 1/20/2026
Enactment date: 1/20/2026 Enactment #: R-26-018
Title: Resolution to Approve Change Order No. 2 with Fonson Company, Inc. for the Westgate Watermain Replacement Project (Additional $220,884.97, Total Contract Amount $2,411,824.68; RFP 25-10)
Attachments: 1. Change_Order2_Details_2023-013_Westgate.pdf, 2. Change Order-01_Fonson Company Inc - Westgate (1).pdf, 3. 2025-05-01_Fonson Company Inc - Construction Agreement (2).pdf
Title
Resolution to Approve Change Order No. 2 with Fonson Company, Inc. for the Westgate Watermain Replacement Project (Additional $220,884.97, Total Contract Amount $2,411,824.68; RFP 25-10)
Memorandum
Attached for your review and approval is Change Order No.2 to the construction contract with Fonson Company, Inc. for the Westgate Watermain Replacement Project (RFP 25-10).

On April 7, 2025, City Council approved a construction contract with Fonson company, Inc (R-25-108). This project consisted of over 2,000 linear feet of new watermain, new valves and transferring of water services as well as restoration. The additional contract work included unanticipated higher asphalt and concrete road restoration costs due to the need for additional watermain line stops, locating service leads, and unexpected field conditions. Change Order No.2 ($220,884.97), exceeds the contingency originally approved by Council ($217,000.00). This Change Order No. 2 will bring the total contract amount to $2,411,824.68 and will allow for final payment to the contractor and subsequent closing out of the contract.

Original Contract $2,168,176.91
Change Order 1(previously approved) $ 22,762.80
Change Order 2 $ 220,884.97
Total $2,411,824.68

Budget/Fiscal Impact: Funding for the project and this change order is included in the FY25-26 Capital Improvements Plan. It will be funded through the approved Water Supply System Fund and the Street, Bridge and Sidewalk Millage.
Staff
Prepared by: Nicholas Hutchinson, P.E., City Engineer
Reviewed by: Jordan Roberts, Public Services Area Administrator
Approved by: Milton Dohoney Jr., City Administrator
Body
Whereas, City Council approved a construction contract (R-25-108) with Fonson Company, Inc. in the amount of $2,168,176.91 for the Westgate Watermain Replacement Project (RFP 25-10);

Whereas, Additional work is needed for the completion of the project;

Whereas, The existing approved contingency amount of $21...

Click here for full text