File #: 24-1933    Version: 1 Name: 12/2/24 Resolution to Amend the Contract with Melink Solar, LLC. to Cover Additional Project Costs for Solar Installation at Ann Arbor Airport for an Additional Cost of $24,842.49 (Total Contract amount: $785,882.49)
Type: Resolution Status: Consent Agenda
File created: 12/2/2024 In control: City Council
On agenda: 12/2/2024 Final action:
Enactment date: Enactment #:
Title: Resolution to Approve Change Order No. 1 to the Contract with Melink Solar, LLC to Cover Additional Project Costs for Solar Installation at Ann Arbor Airport for an Additional Cost of $24,842.49 (Total Contract amount: $785,882.49)
Attachments: 1. Change Order_Melink Solar.pdf, 2. Melink_Change Request.pdf, 3. 2023-12-22_MELINK SOLAR LLC - Construction Agreement (Airport).pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Resolution to Approve Change Order No. 1 to the Contract with Melink Solar, LLC to Cover Additional Project Costs for Solar Installation at Ann Arbor Airport for an Additional Cost of $24,842.49 (Total Contract amount: $785,882.49)
Memorandum
In November of 2023, City Council approved a contract with Melink Solar, LLC to design and install solar installations at the Ann Arbor Airport. In the course of this work, it was discovered that the junction box needed replacement and rerouting and that additional fees were required to shut down the airport during the interconnection process. These additional tasks and fees increase the cost of the project by $24,842.49. Because there was no administrative contingency provision in the resolution approving the original contract, staff are seeking City Council's authorization to increase the contract amount for solar installations at the Ann Arbor Airport from $761,040.00 to $785,882.49. In addition, staff are requesting the addition of a small administrative contingency to this contract in case other changes are needed in the future.

Budget/Fiscal Impact: The Office of Sustainability and Innovations is able to absorb the budget increase of $24,842.49 in our existing Fiscal Year 2025 budget.
Staff
Prepared by: Missy Stults, Sustainability and Innovations Director
Reviewed by: Kim Hoenerhoff, Financial Analyst
Reviewed by: Valerie Jackson, Assistant City Attorney
Approved by: Milton Dohoney Jr., City Administrator
Body
Whereas, In late 2023, Ann Arbor City Council unanimously approved a Contract with Melink Solar, LLC to design and install solar and energy storage systems at the Ann Arbor Airport;

Whereas, In conducting this work, Melink Solar, LLC discovered complicated electrical system configurations that require additional work outside the original scope of services;

Whereas, City staff in the Office of Sustainability and Innovations and across the City are working to adopt clean energy wherever ...