Resolution to Increase the Cost Sharing Total with the City of Ann Arbor for the North Main Street Transportation Study
Memorandum
DDA staff recommends increasing the North Main Street Transportation Cost Share total to include contingency funding, increasing the DDA’s funding commitment by $4,300 from $258,000 to $262,300.
Background
The DDA Board approved a cost-sharing agreement with the City of Ann Arbor for the North Main Street Transportation Study on September 3rd, 2025. The DDA agreed to contribute 43% ($258,000) of the total study cost.
Including a 10-12% contingency on all contracts is standard protocol. The cost share agreement was drafted and executed without a contingency. The City is now requesting the inclusion of a small contingency to close out the project. If approved, the total cost-sharing commitment would be increased by $10,000, with the DDA’s portion at 43% or $4,300.
Budget/Fiscal Impact
The DDA’s portion of the cost allocation for this contract will increase by $4,300 for a total of $262,300. The funding capacity for this contract is available in the approved DDA capital budget.
Body
Whereas, On September 3, 2025, the DDA Board approved a cost-sharing agreement with the City of Ann Arbor for the North Main Street Transportation Study, not to exceed $258,000;
Whereas, The City is now requesting a $4,300 increase in the DDA’s funding commitment;
Whereas, Funding for the increase is included in the approved capital budget of the DDA TIF Fund;
Whereas, This value change can be made without an amendment to the original agreement;
RESOLVED, That the DDA Board approves modifying the cost sharing commitment with the City of Ann Arbor from $258,000 to $262,300 from the DDA TIF Fund;
RESOLVED, That the Executive Director be authorized to take necessary administrative actions to implement this resolution.