Title: Resolution to Approve a Construction Contract with Bailey Excavating, Inc. for the Ann Street Improvements Project ($6,312,780.85) and to Appropriate $2,000,000.00 from the Street, Bridge, Sidewalk Millage Fund, $1,580,000.00 from the Stormwater Fund, $1,961,000.00 of Funding from the Downtown Development Authority (8 Votes Required)
Attachments: 1. RFP 26-03_Ann Street Improvements_Contract.pdf, 2. RFP 26-03 Ann Street Construction Prop Eval Summary.pdf, 3. RFP 26-03 Ann Street Project Location.pdf, 4. Ann Street Improvements - Cost Sharing Agmt with DDA 2-25-26 v3.1.pdf
Title
Resolution to Approve a Construction Contract with Bailey Excavating, Inc. for the Ann Street Improvements Project ($6,312,780.85) and to Appropriate $2,000,000.00 from the Street, Bridge, Sidewalk Millage Fund, $1,580,000.00 from the Stormwater Fund, $1,961,000.00 of Funding from the Downtown Development Authority (8 Votes Required)
Memorandum
Attached for your review and approval, please find a resolution to approve a construction contract between the City of Ann Arbor and Bailey Excavating, Inc. in the amount of $6,312,780.85 for the Ann Street Improvements Project (RFP 26-03).

The Ann Street Improvements Project, from North First Street to North Fifth Avenue includes the following elements and (funding sources):
* Water main and related appurtenances replacement (Water Supply System Funds)
* Infiltrating stormwater system installations and select stormwater system improvements (Stormwater Funds)
* Road resurfacing, curb replacement - including removal of the entire curb cut at 201 N Main St., - bump-out additions at intersections to comply with Vision Zero initiatives, midblock crosswalk by parking structure, sidewalk and ramp replacements (Street, Bridge, and Sidewalk Millage Funds)
* Streetscape improvements in the amenity zone from Ashley Street to Fifth Avenue, including new and replaced streetlights, brick pavers, tree grates, and benches. (DDA Funds)
* A fully ADA accessible on-street parking space and approach and sidewalk replacement of the Ann Street entrance to the Ann-Ashley parking structure. (DDA Parking Funds)

The construction of the project is scheduled in three phases to minimize traffic and business impacts and to coordinate with other downtown capital projects:

* Stage 1: April to June 2026; all work from First St. to Main St.
* Stage 2: July (after Art Fair) to August 2026; all work in Main St. and Ann St. intersection.
* Stage 3: August to November 2026; all work from Main St. to Fifth Ave.

Annual events on Main Street and Ann S...