Ann Arbor logo
File #: 22-0774    Version: 1 Name: 6/6/22 Meter Transmission Unit Purchase
Type: Resolution Status: Passed
File created: 6/6/2022 In control: City Council
On agenda: 6/6/2022 Final action: 6/6/2022
Enactment date: 6/6/2022 Enactment #: R-22-180
Title: Resolution to Approve a Purchase Order to Aclara Technologies LLC for the Purchase of Meter Transmission Units ($200,000.00)
Attachments: 1. Aclara Sole Source Letter to Ann Arbor_04.15.2022 (TS).pdf, 2. Ann Arbor - MTU Quote.pdf
Title
Resolution to Approve a Purchase Order to Aclara Technologies LLC for the Purchase of Meter Transmission Units ($200,000.00)
Memorandum
Attached for approval is a resolution authorizing a purchase order with Aclara Technologies LLC for the purchase of Meter Transmission Units (MTU's) in the amount of $200,000.00.

Aclara Technologies LLC is the sole manufacturer of the Aclara Fixed Network Advanced Metering Infrastructure (AMI) System installed to read the City's water meters. Each MTU is connected to a water meter to transmit readings to a Data Collector Unit (DCU). These products are proprietary and are not compatible with any other AMI system.

This resolution will authorize the purchase of up to 2000 MTU's necessary to complete the Water Meter and MTU Replacement Program and to provide inventory for new customer installations. Pricing is firm for orders placed through July 31, 2022.

Aclara Technologies LLC complies with the City's Non-Discrimination ordinance.

Budget/Fiscal Impact: The Capital Improvements Plan includes the Water Meter and MTU Replacement Program (UT-WS-14-17) and Large Water Meter Replacement Project (UT-WS-22-20). Funding for this purchase is included in the approved Water Supply System and Sewage Disposal Capital Budgets and Water Supply System and Sewage Disposal Operations and Maintenance Budgets.
Staff
Prepared by: Paul Matthews, Public Works Assistant Manager
Reviewed by: Molly Maciejewski, Public Works Unit Manager
Brian Steglitz, Interim Public Services Area Administrator
Approved by: Milton Dohoney Jr., Interim City Administrator
Body
Whereas, The Public Works needs to purchase Meter Transmission Units (MTU's) to collect water and sewer use data;

Whereas, Aclara Technologies LLC is the sole manufacturer of the Aclara Fixed Network Advanced Metering Infrastructure (AMI) System installed to read the City's water meters;

Whereas, Additional MTU's are necessary to complete the W...