File #: 25-1793    Version: 1 Name: 11/17/25 - Contract with PPE for the Screw Pump Replacement Project
Type: Resolution Status: Passed
File created: 11/17/2025 In control: City Council
On agenda: 11/17/2025 Final action: 11/17/2025
Enactment date: 11/17/2025 Enactment #: R-25-406
Title: Resolution to Approve a Construction Contract with Process Piping & Equipment, Inc. for the Screw Pump Replacement Project (RFP #25-38, $2,769,400.00)
Attachments: 1. 2025-10-15 PPE Contract for Screw Pump.pdf, 2. RFP_25_38_AA_WRRF_IFB_Specs_20250808.pdf, 3. 2025-08-19 RFP 25-38 Plans.pdf, 4. 2025-09-24 RFP25-38 Addendum1.pdf, 5. 2025-10-10 RFP25-38 Eval Results Form v3.2.pdf, 6. Executed General Services Agreement, 7. Executed Change Order No. 1
Title
Resolution to Approve a Construction Contract with Process Piping & Equipment, Inc. for the Screw Pump Replacement Project (RFP #25-38, $2,769,400.00)
Memorandum
Attached for your approval is a resolution to approve a construction contract with Process Piping & Equipment, Inc. (PPE), in the amount of $2,769,400.00 for the Water Resource Recovery Facility (WRRF) Screw Pump Replacement Project.

The Approved Capital Improvements Plan (CIP) contained the Screw Pump Replacement Project (UT-SN-26-09) project. This project evaluated the condition of existing screw pumps and adjacent gates at the Raw Sewage Lift Station and the Equalization & Retention building of the WRRF.

As a result of the inspection of the existing screw pumps in the summer of 2024, it was evident that screw pumps #1, 2 and 3 at the Raw Sewage Lift Station and the screw pumps #6, 7 & 8 at the Equalization and Retention Building were in poor condition and required replacement. In addition, the corresponding slide gates required repair or replacement.

Hubbell, Roth & Clark, Inc. (HRC) created bid documents and plans detailing the work necessary to complete the replacement of the six screw pumps.

Solicitation of Proposals
RFP No. 25-38 was prepared along with project specific plans and contract documents. On October 8, 2025, four responsive proposals were received for this work. A selection committee comprised of WRRF staff reviewed the responsive proposals and determined which respondent was the best value based on the following criteria (as laid out in ORD-21-41, adopted by Council on January 3, 2022):

? Qualifications, Experience & Accountability (20%)
? Workplace Safety (20%)
? Workforce Development (20%)
? Social Equity & Sustainability (20%)
? Schedule of Pricing/Cost (20%)

After reviewing and scoring the proposals, staff ranked the respondents in the following order:

1. Process Piping & Equipment, Inc.
2. Monroe Plumbing & Heating Company
3. Midwest Power Systems, Inc.
4. Heaney ...