The City of Ann Arbor Water Treatment Plant (WTP) located at 919 Sunset Road has two DTE electrical feeds for redundancy purposes. DTE has been constructing electrical improvements throughout the City and a part of that work includes upgrading both electrical feeds to the WTP with the goal of improving reliability. This proposed easement allows DTE to install their new Buckler electrical feed to the WTP to replace the aging Argo electrical service. The easement is sized to accommodate a new transformer and underground cabling, ultimately feeding the WTP primary switchgear. This work is necessary to continue redundant power feeds to the WTP which is a critical component for reliable water supply.
The easement has been positioned to have minimal impact to the WTP and its future site plans. The construction work should have minimal impact to the WTP and its neighbors. DTE will be directional drilling the underground cabling in an effort to minimize impact to the tree line on City property that provides screening to the neighbors.
Staff
Prepared by: Glen Wiczorek, Senior Utilities Engineer and
Michele Yanga, Paralegal
Reviewed by Christopher Frost, Senior Assistant City Attorney
Approved by: Milton Dohoney Jr., City Administrator
Body
Whereas, The City of Ann Arbor is the owner of the Water Treatment Plant ("WTP") located at 919 Sunset Road, Ann Arbor, MI 48103;
Whereas, DTE Electrical Company has determined that construction of the Buckler electrical feed to the WTP to replace the aging Argo electrical service is necessary to continue redundant power feeds to the WTP;
Whereas, DTE Electrical Company has requested an easement for the construction and maintenance of electrical utility service located at the WTP;
Whereas, City staff have reviewed the request and recommend approval of the grant of easement...