File #: 24-1469    Version: 1 Name: 10/7/24 PSA with OHM Advisors for Sanitary Comp Plan
Type: Resolution Status: Passed
File created: 10/7/2024 In control: City Council
On agenda: 10/7/2024 Final action: 10/7/2024
Enactment date: 10/7/2024 Enactment #: R-24-388
Title: Resolution to Approve a Professional Services Agreement with OHM Advisors for Engineering Services for the Sanitary Sewer Collection System Comprehensive Plan ($866,165.00)
Attachments: 1. RFP_24-40_published.pdf, 2. OHM for AnnArbor_SewerMasterPlan__Technical.pdf, 3. OHM ADVISORS - Professional Services Agreement (PSA).pdf, 4. Exhibit A_Scope of Services.pdf, 5. Exhibit B_Fees.pdf
Title
Resolution to Approve a Professional Services Agreement with OHM Advisors for Engineering Services for the Sanitary Sewer Collection System Comprehensive Plan ($866,165.00)
Memorandum
Attached for your review and approval is a resolution to authorize a Professional Services Agreement with OHM Advisors to create a comprehensive plan for the City's sanitary sewer collection system and to update the city's hydraulic model.

The goal of this project is to ensure a sustainable sanitary sewer collection system that is protective of the public health while maintaining an acceptable level of service. This will be accomplished by analyzing current and future population projections, sanitary sewer data, and by updating the sanitary sewer system's hydraulic model. When complete, the plan will be used to strategically plan and budget for capacity related improvements to ensure a sustainable sanitary sewer collection system for current demand and future growth needs.

The City issued a Request for Proposal (RFP #24-40) in June 2024 for selecting a consultant to perform engineering services for the above project. Proposals were received from three (3) firms on July 11, 2024. A staff selection committee reviewed the proposals and determined OHM Advisors the most qualified for the work according to several criteria:
? Professional Qualifications (20%)
? Past Involvement with Similar Projects (20%)
? Work Plan (40%)
? Fee Proposal (20%)

The project is anticipated to be completed in early 2026. Additional project budget is requested to retain OHM Advisors for a three (3) year period following the completion of this project for as-needed hydraulic modeling services as outlined in the RFP. These as-needed services may include future updates to the hydraulic model; system operation troubleshooting, development impact analysis, etc.

Budget/Fiscal Impact: Funding is available in the FY25 Systems Planning Sewage Disposal Fund Operations and Maintenance Budget and...