File #: 20-0412    Version: 2 Name: 4/6/20 - WTP SCADA Modernization Project
Type: Resolution Status: Passed
File created: 4/6/2020 In control: City Council
On agenda: 4/6/2020 Final action: 4/6/2020
Enactment date: 4/6/2020 Enactment #: R-20-110
Title: Resolution to Approve an Amendment to the Progressive Design-Build Agreement with J. Ranck Electric, Inc. for Phase 2 of the Water Treatment Plant SCADA System Modernization Project and Appropriate Water Supply System Fund Balance ($4,126,502.79) (8 Votes Required)
Attachments: 1. SCADA CIP - Design-Builder - Amendment 01 - 20200309.pdf, 2. CONTRACT - 0 for J. RANCK ELECTRIC, INC. - WATER TREATMENT 3-6-2019.pdf, 3. R-19-030 Legislation Details (With Text).pdf, 4. WTP SCADA Council Memo_20200406.pdf
Title
Resolution to Approve an Amendment to the Progressive Design-Build Agreement with J. Ranck Electric, Inc. for Phase 2 of the Water Treatment Plant SCADA System Modernization Project and Appropriate Water Supply System Fund Balance ($4,126,502.79) (8 Votes Required)
Memorandum
This memorandum and resolution request approval of an amendment to a progressive design-build agreement with J. Ranck Electric, Inc. to provide professional engineering services for the Water Treatment Plant Supervisory Control and Data Acquisition (SCADA) System Modernization Project (UT-WS-16-19) for a total of $4,126,502.79.

The SCADA System Modernization Project will replace over 20-year old legacy Programmable Logic Controllers (PLC's) and SCADA computer systems with new, modern components capable of additional functionality and integration with other plant software packages and equipment. The PLC's and associated equipment were installed in 1997 and production of all critical components has been discontinued by the manufacturer and are no longer supported. This project will improve the overall reliability of plant control functions, add more data logging and aggregation, integrate the SCADA system with other plant software applications, and comply with industry standard security protocols.

In September 2018, the City issued a request for proposal for the Design-Builder role in the Water Treatment Plant SCADA System Modernization Project. This project is a Progressive Design-Build Project that utilizes a Design-Builder to provide design services at a fixed price for Phase I of the project. At the completion of Phase I, the Design-Builder submits a not-to-exceed contract price to complete the balance of design and construction. This firm price is provided with open book pricing for consideration by the city.

The not-to-exceed contract price negotiated with the city at the conclusion of Phase 1, is $4,126,502.79.

The City worked collaboratively with the Design-Builde...