Ann Arbor logo
File #: 24-2156    Version: 1 Name: 2/18/25 - Change Order No. 2 for the FY24 CPM Project
Type: Resolution Status: Passed
File created: 2/18/2025 In control: City Council
On agenda: 2/18/2025 Final action: 2/18/2025
Enactment date: 2/18/2025 Enactment #: R-25-042
Title: Resolution to Approve Change Order No. 2 with Strawser Construction Inc. for the Annual Street Preventative Maintenance Program FY2024; ($150,477.12 Increase, Total Contract Amount $1,850,477.12)
Attachments: 1. 2023-020 Street PM-FY2024 CM2_FINAL.pdf

Title

Resolution to Approve Change Order No. 2 with Strawser Construction Inc. for the Annual Street Preventative Maintenance Program FY2024; ($150,477.12 Increase, Total Contract Amount $1,850,477.12)

Memorandum

Attached for your review and approval is a contract modification (change order) to the construction contract with Strawser Construction Inc. for the Annual Street Preventative Maintenance Program FY2024 (RFP 22-37).

 

This program consists of performing pavement preservation activities including hot mix asphalt (HMA) pavement repair patching, crack and joint filling, cape seal surface treatments, pavement marking restoration and other related work on select Major and Minor (Local) streets throughout the city that are considered suitable for this work based on condition assessments and PASER ratings.

 

Final quantities for this contract were balanced via Change Order No. 1 in the amount $150,000.00, which was approved administratively within the allotted contingency for the contract extension. Change Order No. 2 involves work to restore specialty pavement markings for bike lanes and related facilities, and other markings that were disturbed by the pavement preservation activities. Quantity increases and decreases are primarily due to errors and omissions, field conditions encountered during construction, and value-added work.

 

The initial contract award, including contingency, equaled $1,700,000.00. The total change order amount for Change Orders 1 and 2 is $300,477.12, which exceeds the contingency originally approved by City Council ($150,000.00) by $150,477.12. Change Order No. 2 will revise the total final contract amount to $1,850,477.12.

 

Budget/Fiscal Impact: Funding for this program and change order is included in the FY2023-2028 Capital Improvements Plan (TR-SC-22-12). Funding is available in the approved Major Streets Fund, Local Streets Fund, and Street, Bridge and Sidewalk Millage Fund.

Staff

Prepared by:         Nicholas Hutchinson, P.E., City Engineer

Reviewed by:        Sue F. McCormick, Interim Public Services Area Administrator

Approved by:        Milton Dohoney Jr., City Administrator

Body

Whereas, Based upon condition assessments and PASER ratings of the existing pavements there is a demonstrated need to perform pavement preservation activities and associated work on suitable streets throughout the city;

 

Whereas, The work included in Change Order No. 2 is required to complete the project;

 

Whereas, Funding for this change order is available in the approved Major Streets Fund, Local Streets Fund, and Street, Bridge and Sidewalk Millage Fund.

 

Whereas, The existing approved contingency amount of $150,000.00 is insufficient to cover the additional work in Change Order No. 2; and

 

Whereas, Strawser Construction Inc. has submitted all required Non-Discrimination, Prevailing Wage, Living Wage, and Conflict of Interest Disclosure forms and complies with the requirements of the City’s Non-Discrimination, Prevailing Wage and Living Wage ordinances;

 

RESOLVED, That City Council approve Contract Modification (Change Order) No. 2 to the construction contract with Strawser Construction Inc. in the amount of $150,477.12 for additional work on the Annual Street Preventative Maintenance Program FY2024 (RFP 22-37); and

 

RESOLVED, That the City Administrator be authorized to take the necessary administrative actions to implement this resolution.