File #: 24-2012    Version: Name: 1/6/25 - Huron River Dr. Culvert Spending Authorization Increase
Type: Resolution Status: Passed
File created: 1/6/2025 In control: City Council
On agenda: 1/6/2025 Final action: 1/6/2025
Enactment date: 1/6/2025 Enactment #: R-25-006
Title: Resolution to Increase Purchasing Authority on the Construction Contract with E.T. MacKenzie Company for the Huron River Drive Culvert Replacement Project, RFP 24-20; ($15,765.62 Increase, Total Contract Amount $650,241.62)
Attachments: 1. 2024.05.04 Huron River Culvert Replacement Cover Sheet Add 1.pdf, 2. 2024.11.22 Huron Culv Change Order #6 PM Signed.pdf

Title

Resolution to Increase Purchasing Authority on the Construction Contract with E.T. MacKenzie Company for the Huron River Drive Culvert Replacement Project, RFP 24-20; ($15,765.62 Increase, Total Contract Amount $650,241.62)

Memorandum

Attached for your approval is a resolution authorizing an increase in purchasing authority on the construction contract with E.T. MacKenzie Company for the Huron River Drive Culvert Replacement Project, RFP 24-20.

 

This project consists of replacing 2 each failed culverts (24” and 12”) under Huron River Drive west of the Barton Pond parking lot, with a pair of parallel elliptical culverts (30” equivalent). The project ran into complications with shutting down the exiting water main which needed to be lowered, requiring additional line stops and using those line stops use for a longer period of time than anticipated. The project also encountered poor soils in the regraded area upstream of the culvert and required the addition use of rip rap to stabilize the grade.

 

The proposed change order includes the additional temporary water main line stops, riprap, and the balancing of all other pay items. The initial contract was approved by Council on June 18, 2024, which included a total spending authorization (contract plus contingency) of $634,746.00. The total cost to complete the work was $650,241.62, which exceeded the authorized spending amount by $15,765.62. If this increase in spending is approved, the final change order will be processed, and the project will be closed out.

 

Budget/Fiscal Impact: Funding for the project is available in the approved Sewage Disposal System Fund and Stormwater Fund Capital Budgets.

Staff

Prepared by:         Nicholas Hutchinson, P.E., City Engineer

Reviewed by:        Sue McCormick, Interim Public Services Area Administrator

Approved by:        Milton Dohoney Jr., City Administrator

Body

Whereas, Additional unforeseen work was required to complete the Huron River Drive Culvert Replacement project;

 

Whereas, E.T. MacKenzie Company has completed the contract work to the satisfaction of City staff;

 

Whereas, The existing approved spending authorization is insufficient to cover the additional work; and

 

Whereas, Funding for the project is available in the approved Sewage Disposal System Fund and Stormwater Fund Budgets;

 

RESOLVED, That City Council approves an increase in the purchasing authority on the contract with E.T. MacKenzie Company in the amount of $15,765.62 for additional work on the Huron River Drive Culvert Replacement Project, (RFP 24-20); and

 

RESOLVED, That the City Administrator be authorized to take the necessary administrative actions to implement this resolution.