RESOLUTION TO ACCEPT A PROPOSAL FROM SCHINDLER ELEVATOR CORPORATION FOR ANN ASHLEY PARKING STRUCTURE ELEVATOR MODERNIZATION
Memorandum
Background: Reliable elevators are very important to the operation of the parking structures. In 2021 the DDA hired an elevator consulting firm, VDA, to inspect parking system elevators and develop a capital maintenance plan. The 2021 plan identified modernization of both Ann Ashley elevators in the next 1-3 years, and funding for this work has been included in the CIP. Obsolete components make repairs difficult and can mean lengthy shutdowns.
Overview & Scope: The attached resolution authorizes the acceptance of a proposal from Schindler Elevator for the modernization of both Ann Ashley elevators with a proposed cost of $695,342.00. The proposal document includes project scope and listing of components. There is a one-year lead time, followed by twelve to fourteen weeks of work per elevator. Funds for this project will be expended across multiple fiscal years.
Body
Whereas, Reliable operation of elevators is integral to the functioning of the parking structures;
Whereas, The DDA’s elevator maintenance contractor, Schindler Elevator Corporation, recommends modernization of both elevators at the Ann Ashley Structure, and this recommendation is in line with reports from VDA Elevator Consulting, a third-party elevator consulting firm that inspects parking system elevators every five years;
Whereas, The Schindler proposal for this work is $695,342.00;
RESOLVED, The DDA Board accepts the proposal in the amount of $695,342.00 for modernization of two elevators at the Ann Ashley Parking Structure, with funds coming from the Parking CIP fund across multiple fiscal years;
RESOLVED, The DDA Board authorizes the DDA Executive Director to execute the necessary documents.
Vendor: Schindler Elevator Corporation
Contract Amount: $695,342.00
Contract Contingency Amount: $0
Change Orders Not-to-Exceed Amount: $0
Fund: Parking CIP
Prepared by: Jada Hahlbrock, DDA Parking Manager