Ann Arbor logo
File #: 11-0453    Version: 1 Name: 5/2/11 E. Stadium Bridges - agrmt. with DTE
Type: Resolution Status: Passed
File created: 5/2/2011 In control: City Council
On agenda: 5/2/2011 Final action: 5/2/2011
Enactment date: 5/2/2011 Enactment #: R-11-176
Title: Resolution to Finalize the Agreement with DTE Energy for the Relocation of Existing Overhead Power Lines for the E. Stadium Boulevard Bridges Replacement Project ($377,966.20)
Attachments: 1. dte - approved resolution for power line relocation - 091019.pdf
Title
Resolution to Finalize the Agreement with DTE Energy for the Relocation of Existing Overhead Power Lines for the E. Stadium Boulevard Bridges Replacement Project ($377,966.20)
Memorandum
Attached, please find a resolution that will approve a purchase order in the final amount of $377,966.20 with DTE Energy, Inc. (DTE) for the overhead power line relocation work associated with the subject project.

On October 19, 2009 the Public Services Area came before you and requested authorization for the City Administrator to enter into an agreement with DTE to relocate existing sub-transmission and distribution power lines pursuant to the East Stadium Boulevard Bridges Replacement Project (R-09-423, copy attached.) The resolution established a not-to-exceed figure of $340,000.00 for the purchase order. The preliminary cost of the power line relocation for the lines over E. Stadium Boulevard was $302,944.00. That cost did not provide for relocation of power lines that fed the University’s Golf Course because DTE had not selected a route nor obtained easements for the lines.

The final cost of this work has now been determined. It is expected that DTE will finalize all work in May, 2011. The balance of costs due DTE is $37,966.20. The total cost for all work performed pursuant to the relocation of overhead power lines associated with this project is $377,966.20.

Funding for this work will come from the approved FY11 Street Repair Millage Capital Budget and is considered local match for State and Federal Funds for the project.
Staff
Prepared by: Homayoon Pirooz, P.E., Manager, Project Management
Reviewed by: Sue F. McCormick, P.E., Public Services Area Administrator
Approved by: Roger W. Fraser, City Administrator
Body
Whereas, It is necessary to temporarily relocate DTE Energy, Inc. power lines so that the E. Stadium Boulevard Bridge over the Ann Arbor Railroad tracks can be safely removed and replaced;

Whereas, The project schedule did not allow for ...

Click here for full text