File #: 17-1482    Version: 1 Name: 10/16/17 - Utility Infrastructure Materials
Type: Resolution Status: Passed
File created: 10/16/2017 In control: City Council
On agenda: 10/16/2017 Final action: 10/16/2017
Enactment date: 10/16/2017 Enactment #: R-17-391
Title: Resolution to Approve the Purchase of Utility Materials from Core and Main LP ($595,239.48; Bid No. ITB-4511)
Attachments: 1. ITB 4511 Bid Tab, 2. ITB 4511 Bid Document

Title

Resolution to Approve the Purchase of Utility Materials from Core and Main LP ($595,239.48; Bid No. ITB-4511)

Memorandum

Attached for your review and consideration for approval is a resolution authorizing up to $595,239.48 for the purchase of Utility Infrastructure Materials from Core and Main LP.  This amount includes the bid price of $496,032.90 and a 20% contingency of $99,206.58.

 

The bid was advertised on the City’s website and on the Michigan Inter-governmental Trade Network (MITN) website. Two (2) bids were received and publically opened on September 21, 2017. Core and Main LP was the lowest responsible bidder on the majority of materials requested. Core and Main LP is also the largest supplier of all the anticipated utility infrastructure materials on the bid.

 

The recommended purchase order to Core and Main for the materials will allow for the purchase of common water, sanitary sewer, and stormwater infrastructure materials to perform routine maintenance, repairs and replacements.

 

Budget Impact: 

Funding is available in the approved FY18 Water Supply System, Sewage Disposal System and Stormwater System Operations and Maintenance budgets and will be available in subsequent annual budgets if approved by Council. 

 

Core and Main LP complies with the City’s Non-Discrimination ordinance.

Staff

Prepared by:   Chris Elenbaas, P.E., Public Works Engineer

Reviewed by:  Molly Maciejewski, Public Works Manager

Reviewed by:  Craig Hupy, Public Services Area Administrator

Approved by:  Howard S. Lazarus, City Administrator

Body

Whereas, The Public Works Unit needs to purchase materials for maintenance, repair and replacement work performed on the water supply, sewage disposal and stormwater systems;

 

Whereas, Two competitive bids (ITB-4511) were received by the Procurement Unit on September 12, 2017, and Core and Main LP was the lowest responsible bidder;

 

Whereas, Funding is available in the approved FY18 Water Supply System, Sewage Disposal System and Stormwater System Operations and Maintenance budgets and will be available in subsequent annual budgets if approved by Council; and

 

Whereas, Core and Main LP complies with the City’s Non-Discrimination ordinance;

 

RESOLVED, That Council approve the issuance of purchase orders to Core and Main for an amount not to exceed $595,239.48 for the purchase of Utility Infrastructure Materials; and

 

RESOLVED, That the City Administrator be authorized to take the necessary actions to implement this resolution.