Ann Arbor logo
File #: 17-0505    Version: 1 Name: 05/01/2017-315-317 S Main Site Plan Approval
Type: Resolution/Public Hearing Status: Passed
File created: 4/4/2017 In control: City Council
On agenda: 5/1/2017 Final action: 5/1/2017
Enactment date: 5/1/2017 Enactment #: R-17-147
Title: Resolution to Approve 315-317 South Main Site Plan, 315 and 317 South Main Street (CPC Recommendation: Approval - 8 Yeas and 0 Nays).
Attachments: 1. 315-317 S Main Staff Report-CPC-with Attachments-031517.pdf, 2. August 2016 HDC Staff Report for 315-321 S Main.pdf, 3. August 2016 HDC Minutes for 315-317 S Main St Site Plan.pdf, 4. September 2016 HDC Staff Report for 315-321 S Main.pdf, 5. September 2016 HDC Minutes-315-317 S Main St Site Plan.pdf
Related files: 16-1160, 16-1287, 16-1493, 17-0436
Title
Resolution to Approve 315-317 South Main Site Plan, 315 and 317 South Main Street (CPC Recommendation: Approval - 8 Yeas and 0 Nays).
Memorandum
Attached is a resolution to approve the 315-317 South Main Site Plan. Approval of this resolution will allow for the construction of a 32,813-square foot building with retail on the ground floor and office on the upper five floors.

Petition Summary:

* The Site Plan proposes to construct a new six-story building with a third-story streetwall. The ground floor is proposed as retail with office on the upper five stories. There are rooftop patios accessible from the fourth, fifth, and sixth floors.
* No vehicle parking is required; four covered spaces are proposed off the rear alley. Four class B bicycle parking spaces are also proposed off the alley.
* An underground infiltration structure will be installed below the rear of the building to accommodate first flush stormwater.

The Historic District Commission, at its meeting of September 8, 2016, granted a Certificate of Appropriateness for the project.

During Planning Commission deliberation, the following questions were raised to be addressed prior to Council approval:

* Will this project impact the pilot organics collection project? No, the proposed development is not anticipated to impact the pilot.
* What will the project's impact be to the City's Development Offset Mitigation program? If the payment-in-lieu method were selected, the payment would be $18,000. Alternatively, the petitioner could remove an equivalent amount of flow through other methods (building demolition, footing drain disconnects, etc.)
* How will pedestrian access be maintained? The City will work with the owner to minimize pedestrian impacts to Main Street through construction of the building.
* Is the proposed development consistent with proposed improvements to the Streetscape and public alley? There are not adopted plans for specific alley improvements in this area.

The...

Click here for full text