Ann Arbor logo
File #: 17-0322    Version: 1 Name: 4/3/17 - FS#1 Generator Engineering
Type: Resolution Status: Passed
File created: 4/3/2017 In control: City Council
On agenda: 4/3/2017 Final action: 4/3/2017
Enactment date: 4/3/2017 Enactment #: R-17-098
Title: Resolution to Approve a Professional Services Agreement between the City and DiClemente Siegel Design Inc. for Work Related to the Fire Station #1 Generator Project ($44,800.00)
Attachments: 1. DSD Contract - FS#1 Generator, 2. FS 1 Generator - DSD Proposal
Title
Resolution to Approve a Professional Services Agreement between the City and DiClemente Siegel Design Inc. for Work Related to the Fire Station #1 Generator Project ($44,800.00)
Memorandum
Attached for your review and approval is a resolution to approve a Professional Services Agreement between the City and DiClemente Siegel Design Inc. (DSD), Southfield, Michigan, in the amount of $44,800.00, for engineering services related to the generator project at Fire Station #1.

This overall project consists of removing and replacing an old diesel powered generator at Fire Station #1 with a new natural gas powered unit; expanding the backup coverage in the building to provide emergency power to all fire operations within the building; removal of the existing diesel fuel storage tank; evaluation and upgrade (if necessary) of transfer switches and electrical panels, natural gas supply and exhaust/ventilation. DSD will provide an evaluation of the Fire Station electrical systems, complete design and technical specifications and provide construction administration for the project.

Fire Station #1 has a second natural gas powered generator that provides power to the emergency dispatch operations (9-1-1) call center. That generator was installed and is maintained by the dispatch center and will not be affected by our project.

An RFP was issued on February 8, 2017 for engineering services for this project and DSD was the sole responder. The City has used DSD in the past and found them to be both competitive in their pricing and competent in their field. The resolution includes a recommended 10% project contingency of $4,480.00 to cover potential contract change orders to be approved by the City Administrator if necessary.

The $230,000.00 project was included in the City's Capital Improvement Plan and funding is available in the General Fund Capital Budget.

DiClemente Siegel Design Inc. complies with the requirements of the City's living wage and non-discriminat...