File #: 08-1038    Version: 1 Name: 12/1/08 AT&T Emergency PO/ Telecommunications Relocation
Type: Resolution Status: Passed
File created: 12/1/2008 In control: City Council
On agenda: 12/1/2008 Final action: 12/1/2008
Enactment date: 12/1/2008 Enactment #: R-08-486
Title: Resolution Ratifying the Issuance of an Emergency Purchase Order to AT&T Michigan for the Relocation of Telecommunications Facilities by the City Administrator and Authorizing the City Administrator to take all Necessary Actions for the Relocation of Telecommunication Facilities($58,870.06)
Attachments: 1. ATT RELOCATION 122820.pdf
Title
Resolution Ratifying the Issuance of an Emergency Purchase Order to AT&T Michigan for the Relocation of Telecommunications Facilities by the City Administrator and Authorizing the City Administrator to take all Necessary Actions for the Relocation of Telecommunication Facilities($58,870.06)
Memorandum
The attached resolution ratifies and approves the emergency issuance of a purchase order to AT&T Michigan (AT&T) for the relocation of AT&T telecommunications facilities in order to accommodate the planned construction of the Ann Arbor Municipal Center and the signing of the accompanying AT&T Estimate of Cost and Authority for Work authorizing the relocation of telecommunications services.

The Larcom building currently receives AT&T services through the South Telecommunications Facility and Entrance, located north of Huron St. at the southwest corner of the promenade deck. It is necessary to abandon this South Telecommunications Facility and Entrance to accommodate the Ann Arbor Municipal Center Project.

In order to continue to provide the necessary telecommunications services, including voice, data, traffic signal and 800 MHz dispatching services, a new East Telecommunications Facility and Entrance has been constructed along the south and east sides of the Larcom building. The current AT&T services, which include voice and public safety data services, will be relocated to the East Telecommunications Facility and Entrance.

AT&T’s quote of $58,870.06 for this custom relocation work was received by the City’s Information Technology Service Unit on Friday November 14, 2008.

With Ann Arbor Municipal Center construction planned to begin during the first week of March and this telecommunications facilities project having a 10 to 12 week turnaround time and AT&T requiring payment from its customers prior to start of any special construction project, it was necessary to execute an Emergency Purchase Order to AT&T Michigan in the amount of $58,870.06 to...