Ann Arbor logo
File #: 16-1675    Version: 1 Name: 1/3/17 Stone School Special Assessment Confirmation
Type: Resolution/Public Hearing Status: Passed
File created: 1/3/2017 In control: City Council
On agenda: 1/3/2017 Final action: 1/3/2017
Enactment date: 1/3/2017 Enactment #: R-17-007
Title: Resolution No. 4 - Confirming the Stone School Road Sidewalk Special Assessment
Attachments: 1. Stone School Rd Sidewalk Special Assessment Roll 11-16
Title
Resolution No. 4 - Confirming the Stone School Road Sidewalk Special Assessment
Memorandum
Attached for your review and approval is Resolution No. 4 confirming the Special Assessment Roll for the Stone School Sidewalk - Special Assessment, District No. 47, File No. 2015-033

In accordance with the City's Non-Motorized Plan and Complete Street approach, it is proposed to install a new sidewalk to close gaps and provide a continuous pedestrian connection along the west side of Stone School Road from Birch Hollow Drive to Packard. A letter was mailed to the affected property owners to describe the project on June 14th and 16th of 2016. Included in the discussions were the shared costs to property owners for the addition of sidewalk, the estimated total project cost, property assessments and the work schedule. Resolution 2 establishing the estimated cost of the project and the estimated project revenue sources and directing the preparation of the special assessment roll was approved by Council on August 15, 2016. Resolution No. 3, approved by Council on December 5, 2016 scheduled the Public Hearing for January 3, 2017.

Per information given to the affected owners, it is recommended that the property share be in three payments.
Staff
Prepared by: David Petrak, Assessor
Reviewed by: Tom Crawford, Financial Services Administrator and CFO
Approved by: Howard S. Lazarus, City Administrator
Body
Whereas, City Council, after due and legal notice, has met for the purpose of reviewing the Special Assessment Roll prepared for the purpose of assessing the private property's share of the cost of the sidewalk described as follows: New sidewalk on the west side of Stone School Road between Birch Hollow Drive and Packard Road. The project also includes the replacement of a deteriorated asphalt sidewalk on the west side of Stone School Road between Packard Road and Eisenhower Parkway, District No. 47, File No. 2015-033;

Whereas, City Council has hea...

Click here for full text