File #: 08-0898    Version: 1 Name: 10/20/08 - Meter Replacement to United Water
Type: Resolution Status: Passed
File created: 10/20/2008 In control: City Council
On agenda: 10/20/2008 Final action: 10/20/2008
Enactment date: 10/20/2008 Enactment #: R-08-430
Title: Resolution to Award a Contract for the Master Meter Replacement Project to United Water - NACO ($68,301.00)
Attachments: 1. Master Meter Contract.pdf
Title
Resolution to Award a Contract for the Master Meter Replacement Project to United Water - NACO ($68,301.00)
Memorandum
We request your approval of a contract with United Water - NACO for the Master Meter Replacement Project.

The Master Meter Replacement Project is necessary to install five meters that were not included as part of the Automated Meter Reading (AMR) project that began in 2004. These five meters require specialized construction techniques because they are located in below ground meter pits in traffic right-of-ways.

The City received the following five bids for construction services:

United Water - NACO $ 68.301.00
John E. Green Company $117,500.00
Weiss Construction $149,350.00
Sinatech Construction $154,572.00
O’Laughlin Construciton $177,800.00

It is recommended that the bid from United Water - NACO for $68,301.00 be accepted, and that United Water - NACO be awarded the contract for the Master Meter Replacement Project.

Council approved this project and it’s associated budget on March 15, 2004 (R-97-3-04). You are also requested to establish a contingency of $10,000.00 for the United Water - NACO contract for change orders to be approved by the City Administrator. Funds for this project are available in the previously established budget.

United Water - NACO has received Human Rights approval on September 18, 2008, and complies with the living wage ordinance.
Staff
Prepared by: Brian Steglitz, P.E., Sr. Utilities Engineer, WTP
Reviewed by: Sue F. McCormick, Public Services Administrator
Approved by: Roger W. Fraser, City Administrator

Body
Whereas, It is necessary to complete the Master Meter Replacement Project to install five master meters located in below ground meter pits that were not completed as part of the Automated Meter Reading Project;

Whereas, Of the five bids received, United Water - NACO provided the lowest responsible bid in the amount of $68,301.00;

Whereas, United Water - NACO has receive...