File #: 08-0605    Version: 1 Name: 7/07/08 - Resolution to Award PSA to Wade-Trim
Type: Resolution Status: Passed
File created: 7/7/2008 In control: City Council
On agenda: 7/7/2008 Final action: 7/7/2008
Enactment date: 7/7/2008 Enactment #: R-08-288
Title: Resolution to Approve a Professional Services Agreement with Wade Trim, Inc. for Design Engineering Services for the Valhalla Drive Sanitary Sewer Extension Project ($97,062.45)
Attachments: 1. wt psa valhalla drive sanitary sewer extension 080604.pdf, 2. Valhalla Drive Project Location Drawing 080604.pdf
Title
Resolution to Approve a Professional Services Agreement with Wade Trim, Inc. for Design Engineering Services for the Valhalla Drive Sanitary Sewer Extension Project ($97,062.45)
Memorandum
Attached for your review and approval, please find a resolution approving a professional services agreement for design engineering services in the amount of $97,062.45 with Wade Trim, Inc. (WT).

Project UT-SN-06-01, the Valhalla Drive Sanitary Sewer Extension Project, is included in the City's adopted FY08 Capital Budget. The project includes the construction of 8-inch sanitary sewer from Valhalla Drive cross-lots across the University of Michigan’s Golf Course and Driving Range. The proposed sewer will outlet into an existing sanitary sewer located in Golfview Lane. Please see the attached drawing that depicts the project location and the proposed routing of the sanitary sewer.

This project includes the construction of approximately 2,500 lineal feet of 8-inch sanitary sewer to serve the residential properties along Valhalla Drive that have failing septic tanks and tile fields. There are seventeen properties located within the proposed service area. Two of the properties are currently within the City and the remaining parcels are located within an island of Pittsfield Township parcels. All parcels will be required to pay the fixed charge improvement charge in effect at the time for sanitary sewer mains when they connect to the proposed sanitary sewer line. We expect to complete the design of the project this year and construct the project in 2009.

A Request for Proposals was issued from the Project Management Services Unit for nine projects. We received proposals from nineteen consulting engineering firms for the requested projects. A selection committee reviewed the submitted proposals. The selection committee consisted of staff from the Project Management Services Unit. Based on the proposals received, the top three consultant teams were selected ...

Click here for full text