File #: 15-0969    Version: 1 Name: 9/8/15 - - Precision Concrete Change Order
Type: Resolution Status: Passed
File created: 9/8/2015 In control: City Council
On agenda: 9/8/2015 Final action: 9/8/2015
Enactment date: 9/8/2015 Enactment #: R-15-301
Title: Resolution to Approve Change Order No. 1 with Precision Concrete, Inc. (Bid No. 4260) for the 2015 Ramp & Sidewalk Repair Project ($132,000.00)
Attachments: 1. Precision Contract Extension 2015 Executed, 2. Precision Change Order #1
Title
Resolution to Approve Change Order No. 1 with Precision Concrete, Inc. (Bid No. 4260) for the 2015 Ramp & Sidewalk Repair Project ($132,000.00)
Memorandum
Attached for your review and approval is a change order to the Construction Services Agreement with Precision Concrete, In. (Bid No. 4260) for the 2015 Sidewalk Repair Project.

Budget Impact
The project is funded from the approved Street Resurfacing and Sidewalk Repair Millage capital budget. A construction services agreement was approved by City Council on March 16, 2015 for a total authorized amount of $143,000.00. Change Order No. 1 in the amount of $132,000.00, increases the total authorized amount to $275,000.00.

The Sidewalk Cutting Project is in process of repairing deficient sidewalks in approximately 20% of the City in 2015, as part of the fourth year of a 5-year program to perform repairs on the City's entire sidewalk system.

The scope of the work for this contract includes cutting "vaulted" or "displaced" joints in sidewalk slabs where the vertical displacement is greater than 1/2 inch in height. Vertical displacements greater than 1 inch in height are generally considered to be too large for cutting and are typically planned to be removed and replaced with new concrete. By horizontally cutting sidewalk that is in otherwise good condition, full removal and replacement can be avoided. Based on the current unit prices for this year's ramp and sidewalk project, on average the cutting of one transverse joint will save the City about $164 per location compared to full replacement for a typical sidewalk slab.

Quantities of work for sidewalk repairs are based solely on engineers' estimates made at the beginning of the construction season. Field conditions determine the actual amount of work needed. Inspections in the field have found more opportunities to utilize this technology than previously estimated. This increase in authorized cutting quantities provides an opportunity to ext...

Click here for full text