Title: Resolution to Approve Amendment No. 2 with Greeley and Hansen, LLC for Construction Engineering Services at the Wastewater Treatment Plant ($304,940.00)
Attachments: 1. G&H RHI Amend 2 Const Serv .pdf
Title
Resolution to Approve Amendment No. 2 with Greeley and Hansen, LLC for Construction Engineering Services at the Wastewater Treatment Plant ($304,940.00)
Memorandum
Your approval is requested to amend a Professional Service Agreement with Greeley and Hansen, LLC (G&H) for construction engineering services in the amount of $304,940.00 to complete construction of the Residuals Handling Improvements (RHI) project at the City's Wastewater Treatment Plant (WWTP).

The RHI project consists of the renovations identified in the WWTP's Sewage Residuals Management Plan (SRMP). The SRMP is a comprehensive 25-year planning document that provides the basis and schedule for rehabilitation and replacement of major solids handling equipment and systems at the WWTP. Project improvements include demolition and replacement of existing solids handling equipment and systems with more effective and efficient equipment and systems, and complete demolition of the City's sludge incinerator. The RHI is a major plant renovation project included in the City’s Capital Improvements Plan (CIP) for the WWTP. Construction of this project started in January 2009 and is currently 98% complete.

On January 5, 2009, Council approved a construction contract with Sorensen Gross Construction Services, LLC (SG) in the amount of $42,444,927.00 to construct the RHI project. On January 20, 2009 Council approved an agreement with G&H in the amount of $4,225,604.00 to provide construction engineering services for the RHI project. As part of the agreement, G&H provides on-site construction inspectors, submittal reviews, record drawings, change order assistance, construction administration, document management, claims evaluation, equipment training and start-up assistance.
On November 21, 2011, the City Administrator approved Amendment No. 1 to the Agreement with G&H in the amount of $420,123.00 to provide additional construction engineering services including submittal reviews, change order assista...