Ann Arbor logo
File #: 12-0500    Version: 1 Name: 5/7/12 WTP Pump Station
Type: Resolution/Public Hearing Status: Passed
File created: 5/7/2012 In control: City Council
On agenda: 5/7/2012 Final action: 5/7/2012
Enactment date: 5/7/2012 Enactment #: R-12-189
Title: Resolution to Approve City of Ann Arbor Water Treatment Plant West High Service Pump Station Public Project, 919 Sunset Road (CPC Recommendation: Approval - 8 Yeas and 0 Nays)
Attachments: 1. Planning Staff Report with Attachments.pdf
Related files: 12-0423
Title
Resolution to Approve City of Ann Arbor Water Treatment Plant West High Service Pump Station Public Project, 919 Sunset Road (CPC Recommendation: Approval - 8 Yeas and 0 Nays)
Memorandum
Attached is a resolution to approve the City of Ann Arbor Water Treatment Plant West High Service Pump Station Public Project.  This project is included in the 2012-2017 Capital Improvements Plan.
 
Petition Summary:
 
·      This petition proposes construction of a 3-story pump station (2 floors below grade) totaling 5,114 sq. ft.  The service pump station is proposed to be constructed adjacent to the eastern side of the existing administration building.
 
·      The proposed addition will match the existing materials and architecture of the building.  
 
·      No natural features are proposed to be disturbed from this proposal.
 
A neighborhood meeting was held on February 9, 2012.  A summary report of this meeting is included in the Planning staff report.
 
The City Planning Commission, at its meeting of March 20, 2012, passed a resolution finding the above project to adhere to City private development standards and recommended approval of this request.  
 
Attachments:  3/20/12 Planning Staff Report and 3/20/12 Planning Commission Minutes
Staff
Prepared By:  Chris Cheng, City Planner
Reviewed By:  Wendy L. Rampson, Planning Manager and Sumedh Bahl, Community Services Administrator
Body
Whereas, The City of Ann Arbor Public Services Area has requested public project review to construct a 3-story pump station (2 floors below grade) totaling 5,114 sq. ft.; and
 
Whereas, The Ann Arbor City Planning Commission, on March 20, 2012, passed a resolution finding the above project to adhere to City private development standards and recommended approval of this request;
 
RESOLVED, That City Council approve the City of Ann Arbor Water Treatment Plant West High Service Pump Station Public Project, dated February 22, 2012.