File #: 12-0577    Version: 1 Name: 5/21/12 - Thurston Safe Routes to School Grant Application
Type: Resolution Status: Passed
File created: 5/21/2012 In control: City Council
On agenda: 5/21/2012 Final action: 5/21/2012
Enactment date: 5/21/2012 Enactment #: R-12-234
Title: Resolution to Approve the Safe Routes to School Application for Clague School
Title
Resolution to Approve the Safe Routes to School Application for Clague School
Memorandum
Attached for your approval is a resolution for the support of a grant application and commitment of resources for Clague School’s Safe Routes to School initiative. City staff has worked with the Clague safe routes team, including school parents, Community Health Personnel and AAPS staff since 2010 on developing the project. At this time a grant application is prepared and as a part of that MDOT requires a formal commitment from the local agency to go forward.

The proposed project, depending on the scope of approval by the MDOT, includes installation of one (1) Rectangular Rapid Flashing Beacon on Green Road, crosswalk improvements on Nixon Road and the installation of sidewalk along a portion of Nixon Road. This scope was developed by the project team and is supported by the local community. The total request with this application is for $117,500.00, with an average award of $250,000.00 it is likely to be fully funded.

The Safe Routes to School grants are unique in that 100% of the construction costs are included, no local match is required, and improvements may include sidewalk construction. Design and construction inspection however are not covered by grant funding. This work will be provided by the Project Management Services Unit and will be funded by the Alternative Transportation Fund. The following estimates are prepared for a full $117,500.00 award for the construction contract.

Revenue
Federal Surface Transportation Funds (SR2S) - $117,500.00
Alternative Transportation Fund - $28,000.00
TOTAL - $145,500.00

Expense
Contract Construction - $117,500.00
Design & Construction Inspection - $25,000.00
Contingencies - $3,000.00
TOTAL - $145,500.00
Staff
Prepared by: Homayoon Pirooz, P.E., Project Management Manager
Reviewed by: Craig Hupy, Interim Public Services Area Administrator
Approved by: Steven D. Powers, City Administrator
Body
Whereas, The Safe...

Click here for full text