Resolution Approving a Grant of Easement to DTE Energy for a Storm Water Discharge Pipe (Located at Gallup Park) (8 Votes Required)
Memorandum
There is a resolution before you to approve a grant of easement to DTE Energy, a Michigan corporation, for the construction and maintenance of a storm water discharge pipe located in Gallup Park.
The drainage pipeline is for the purpose of discharging water into the Huron River and will run underground from the DTE electrical substation at Geddes and Fuller traversing the gravel access drive to the park directly to the river. The installation is required to meet state/federal regulations for DTE infrastructure improvements.
The terms, conditions, and location of the grant of easement have been reviewed and approved by all required City service areas. DTE is required under the terms of the grant to file copies of “as built’ drawings with the City and copies of all state/federal permits required in connection with construction and any maintenance activities thereafter with the Parks Manager. Uninterrupted access to the park must be maintained at all times under the terms of the easement.
Staff
Prepared by: Andrea Odegaard, Legal Assistant
Reviewed by: Stephen K. Postema, City Attorney
Approved by: Steven D. Powers, City Administrator
Body
Whereas, DTE Energy, a Michigan corporation, has requested an easement for the construction and maintenance of a storm water discharge pipe to be located in Gallup Park for the purpose of discharging water into the Huron River; and
Whereas, The required City service areas have reviewed the request and determined that it is in the City’s best interest to grant the easement;
RESOLVED, That the City of Ann Arbor hereby approve said grant of easement for the construction and maintenance of a storm water discharge pipe located in Gallup Park, said easement being more particularly described as follows:
A 10-foot wide by approximately 50-foot long easement described as fol...