File #: 12-0011    Version: 1 Name: 2/6/12 - E&L Contract Amendment #2 Clarifier 4 & 5 Repair and Paint
Type: Resolution Status: Passed
File created: 2/21/2012 In control: City Council
On agenda: 2/21/2012 Final action: 2/21/2012
Enactment date: 2/21/2012 Enactment #: R-12-053
Title: Resolution for Approval of Amendment No. 2 to the Contract for Structural Repair and Painting of Clarifiers 4 & 5 with E & L Construction Group, Inc. ($139,000.00)
Attachments: 1. co_#2_aawtp_clarifier_4_5_imps_2011-12-16.docx
Title
Resolution for Approval of Amendment No. 2 to the Contract for Structural Repair and Painting of Clarifiers 4 & 5 with E & L Construction Group, Inc. ($139,000.00)
Memorandum
This memorandum and resolution requests approval of Amendment No. 2 to the contract with E & L Construction Group, Inc. for the Structural Repair and Painting of Clarifiers 4 & 5 Project ($139,000.00).

This project replaces the coatings on all structural steel components in Clarifiers 4 and 5 at the Water Treatment Plant. In addition, this project includes replacement of deteriorated handrail, installation of fixed ladders to safely access work areas, repair of a weir ring in Clarifier 5, and removal and replacement of weir plates on the outer launder of Clarifier 5. The metal components in Clarifier 4 and 5 were last coated in the mid-1980’s. The existing coatings have exceeded their expected life by approximately 5 to 10 years.

Council approved the contract with E&L Construction for $322,500.00 and a contingency in the amount of $35,000.00 in November 2009, as part of Resolution No. R-09-464. In May 2011, Amendment No. 1 for a contract deduction of $11,783.16 was approved by the City Administrator, leaving the project contingency balance of $46,783.16. Amendment No. 2 for $139,000.00 will exhaust the project’s contingency and will require Council approval of an additional $92,216.84 to address the necessary change order.

Amendment No. 2 includes the following additional work:

? Removal of mill scale in Clarifier 4;
? Additional testing Services; and
? Additional painting and blasting associated with the poor condition of the steel.

It is recommended that Amendment No. 2 to the contract with E&L Construction in the amount of $139,000.00 be approved.

E & L Construction Group received Human Rights approval on January 25, 2011, and complies with the living wage ordinance.

Funds for this project are to be advanced from the Water Supply System Unobligated Fund Balance to be r...