Resolution No. 4 - Scio Church Improvements Project, Curb and Gutter & Sidewalk Special Assessment District No. 52, File No. 19-0064
Memorandum
Attached and recommended for approval is Resolution 4 confirming the Special Assessment Roll for the Scio Church Improvements Project, Curb and Gutter & Sidewalk Special Assessment District No. 52, File No. 19-0064.
An administrative hearing explaining the project to property owners was held on January 17, 2019. Included in the discussions were cost estimates, property assessments and the work schedule. Resolution No. 1 was previously approved on November 9, 2017. Resolution No. 2 establishing the estimated cost of the project, the estimated project revenue sources and directing the preparation of the special assessment roll was approved by Council on February 4, 2019. Resolution No. 3 scheduled the Public Hearing for July 15, 2019.
Per City ordinance, it is recommended that property special assessments up to $1,200.00 be billed in one installment. Property special assessments over $1,200 shall be divided into equal installments as indicated in Chapter 12, subsection 1:275(2).
Staff
Prepared by: Mark Perry, City Assessor
Reviewed by: Tom Crawford, Financial Services Area Administrator and CFO
Approved by: Howard S. Lazarus, City Administrator
Body
Whereas, City Council, after due and legal notice, has met for the purpose of reviewing the Special Assessment roll prepared for the purpose of assessing the private property's share of the cost of the following described public improvement to be defrayed by Special Assessment: Construction of a new sidewalk system and new curb and gutter along the south side of Scio-Church Road from S. Main Street westerly to S. Seventh Street, Scio Church Improvements Project; Curb and Gutter & Sidewalk Special Assessment District No. 52, File No. 19-0064;
Whereas, That the City Council determine the cost of said improvements, including all incidentals, to be $128,...