Ann Arbor logo
File #: 24-1164    Version: 2 Name: 7/15/24 Amendment 1 to OHM Advisors PSA
Type: Resolution Status: Passed
File created: 7/15/2024 In control: City Council
On agenda: 7/15/2024 Final action: 7/15/2024
Enactment date: 7/15/2024 Enactment #: R-24-292
Title: Resolution to Approve Amendment No. 1 to the Professional Services Agreement with OHM Advisors for General Civil Engineering and Surveying Services (Additional $900,000.00 for a Contract Total of $1,650,000.00)
Attachments: 1. High Level Trunkline Sewer Capacity Improvements Detailed Design 202400606 v2.pdf, 2. First Street Sewer Route Map.pdf, 3. OHM PSA Amendment 1.pdf
Title
Resolution to Approve Amendment No. 1 to the Professional Services Agreement with OHM Advisors for General Civil Engineering and Surveying Services (Additional $900,000.00 for a Contract Total of $1,650,000.00)
Memorandum
This resolution requests approval of Amendment No. 1 to the professional services agreement for General Civil Engineering and Surveying Services with OHM Advisors (OHM). City Council approved a professional services agreement for $750,000.00 with OHM on August 7, 2023, as part of Resolution No. R-23-277.

Under the current contract, OHM has provided engineering services for a variety of projects. They have demonstrated themselves to be experienced in a wide range of disciplines, and they are responsive and cost effective in meeting the diverse needs on complex engineering tasks.

At the City's request, OHM was commissioned by the University of Michigan (UofM) to evaluate impacts to the City's sanitary sewer system as a result of the proposed UofM dorm developments in south campus. Results from this effort indicated a relief sewer will be needed to accommodate the flows from the proposed dorms. This sewer project will also benefit the City as a whole, adding sewer capacity for future growth within the sewer shed. The City created a capital project for this effort, titled the High-Level Trunkline Sewer Capacity Improvements Project.

OHM has completed their preliminary design efforts and, after evaluating several alternatives, a proposed route for the relief sewer was selected along First Street from Washington Street to Miller Avenue. The engineering design for this project must now commence in order to coincide with the expedited timeline of the first phase of the dorm project (August 2026).

Due to the expedited schedule, issuing a Request for Proposal for this design work is not feasible within the required timeframe. Considering OHM's extensive knowledge of the project and the sanitary sewer analysis already performed, staff is re...